Building Future: Referendum Progress
Have You Seen Our New Learning Spaces?
Building Future, Cutting Ribbons
View School Referendum Progress
School Construction Schedule
Henking Timeline
- Week of 6/1/21 – 6/4/21
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week 12/13/21 - 12/18/21
- Week 12/20/21 - 12/25/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/21/22 -2/26/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 - 3/12/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 - 4/2/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week of 6/6/22 - 6/11/22
Week of 6/1/21 – 6/4/21
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Week of 7/19/21 - 7/24/21
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Week of 8/16/21 - 8/21/21
Week of 8/23/21 - 8/28/21
Week of 8/30/21 - 9/4/21
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Week of 9/20/21 - 9/25/21
Week of 9/27/21 - 10/2/21
Week of 10/4/21 - 10/9/21
Week of 10/11/21 - 10/16/21
RB
- Courtyard sheathing complete, continuing with remainder of building
MEP
- Ductwork, in wall rough and roof work
- Jensens, continuing with roof drains and in wall rough
- AMI, starting water lines
Elens & Maichin
- Continue with roofing
Mastership
- Starting MPR
- Beginning with courtyard masonry work
Nelson Fire Protection
- Completed overhead work (10/6) -- ***Minus stub in at existing building, TBD***
Week of 10/18/21 - 10/23/21
RB
- Continue exterior sheathing and air barrier work
- Skylight curbs and chases completed and dried in, coordinate with Elens & Maichin
MEP
- Ductwork, in wall rough and roof work
- Jensen's, continuing with in wall rough
- AMI, starting water lines
Elens & Maichin
- Roof install ongoing
- MPR metal work to begin
Mastership
- Masonry in courtyard ongoing
Madden Glass
- Begin setting window frames at MPR
Week of 10/25/21 - 10/30/21
RB
- Interior wall framing on going
Madden Glass
- Frames to begin arriving for windows
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's:
- In wall rough ongoing
- American:
- Have all exterior rough work complete
- Complete all overhead branch work
- In wall rough on going
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- Courtyard masonry ongoing - MOCK UP READY FOR REVIEW
- Begin MPR masonry
Week of 11/1/21 - 11/6/21
RB
- Interior wall framing ongoing
Madden Glass
- Begin install where openings are ready
- ***Large units with doors have been boarded up, material due in January***
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's
- In wall rough ongoing
- American:
- In wall rough on going
- Complete all overhead branch work
- Have all exterior rough work complete
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- Courtyard masonry ongoing
- Begin MPR masonry
Week of 11/8/21 - 11/13/21
RB
- Interior wall framing ongoing
Madden Glass
- Begin install where openings are ready
- ***Large units with doors have been boarded up, material due in January***
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's
- In wall rough ongoing
- American:
- Have all exterior rough work complete
- Complete all overhead branch work
- In wall rough ongoing
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- East and west elevations masonry
- MPR masonry ongoing
Week of 11/15/21 - 11/20/21
RB
- Complete interior wall framing EOW 11-12
MEP
- Jensens
- Complete in wall rough 11-12
- Call for inspections EOW 11-15
- American
- Complete all rough EOW 11-12
- Ready for inspections week of 11-15
- DeKalb
- Complete all rough duct work overhead equipment, etc and ready for drywall week of 11-22
- AMI
- Have all overhead and inwall work complete
- Ready for drywall week of 11-22
- Inspections
- AMI
- Complete all rough duct work overhead equipment, etc and ready for drywall week of 11-22
- Nelson
- Complete roof EOW
- Fascia and soffit work underway at MPR
- Mastership
- MPR complete
- East elevation complete
- S. elevation ongoing
Week of 11/22/21 - 11/27/21
RB
- Soffit framing ongoing
- Misc. framing of columns etc are ongoing
- First coat of mud complete at corridors
- Taping continues as availabl
- Drywall ongoing all areas
Monarch
- Door frames install ongoing (as available)
Madden Glass
- Continue install of available windows
MEP
- Jensens
- Continue with in-wall rough at large washrooms and storage area in MPR
- American
- Continue to follow behind RB at soffits to complete piping tie-ins
- DeKalb
- Continue with fan coil install, pipe and duct insulation ongoing overhead, instaff double wall duct in MPR
- AMI
- Continue with gas pipe to new addition RTU locations, continue with water pipe tie ins at fan coils
- Elens & Maichin
- MPR shingles ongoing
- Fascia and soffit metal work ongoing
- Mastership
- N. elevation of MPR corridor above existing building ongoing
Week of 11/29/21 - 12/4/21
RB
- Soffit framing ongoing
- Misc. framing of columns etc are ongoing
- First coat of mud complete at corridors
- Taping continues as availabl
- Drywall ongoing all areas
Monarch
- Door frames install ongoing (as available)
Madden Glass
- Continue install of available windows
MEP
- Jensens
- Continue with in-wall rough at large washrooms and storage area in MPR
- American
- Continue to follow behind RB at soffits to complete piping tie-ins
- DeKalb
- Continue with fan coil install, pipe and duct insulation ongoing overhead, instaff double wall duct in MPR
- AMI
- Continue with gas pipe to new addition RTU locations, continue with water pipe tie ins at fan coils
Elens & Maichin
- MPR shingles ongoing
- Fascia and soffit metal work ongoing
Mastership
- S. elevation complete and washed
- All equipment, debris and remaining materials removed from premises by EOW
Week of 12/6/21 - 12/11/21
RB
- Soffit framing and skylight framing on going
- Drywall on going all areas
- Taping ongoing in areas available
- In wall insulation on going
Monarch
- Complete Door frame install on going.
Madden Glass
- Continue install of available windows & glass ongoing
- MPR glass due in week of 12-20
Jensen’s
- Pipe insulation ongoing
- Final in-wall rough inspection Monday 12-6
American
- Wire feeding on going
DeKalb
- Insulation on going
AMI
- Insulation on going
Elens & Maichin
- MPR Fascia wood blocking on going
- Metal Cooping on going-currently being fabricated, begin installing this week.
Week 12/13/21 - 12/18/21
RB
- Soffit framing and skylight framing on going, to be completed this week
- Drywall on going all areas
- In wall insulation to be completed
Madden Glass
- Continue install of available windows & glass on going
Jensen’s
- Complete Pipe insulation
American
- Wire feeding on going
DeKalb
- Complete overhead Insulation
AMI
- Complete overhead Insulation on going
Elens & Maichin
- MPR Fascia wood blocking to be completed
- Metal Cooping to be completed
- Waiting on fascia and soffit metal
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
Week 12/20/21 - 12/25/21
RB
- Drywall on going in remaining areas
- Taping on going in available areas
- Painting-block fill to begin in MPR
Madden Glass
- Continue install of available windows & glass on going
- MPR upper window glass due in
American
- Wire feeding to be completed
DeKalb
- RTU install expected in January
Elens & Maichin
- Install Shingles
- Install metal wall panels
Week of 1/10/22 - 1/15/22
RB
May Decorating
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
Smart Interiors
- Final taping in MPR
- Taping in corridors.
Consolidated
Regency Tile
- Start installing bathroom wall tile in classrooms A1-A8
Madden Glass
- Continue install of available windows & glass on going
- MPR window glass completed week of 12-27 ***minus entryways***
American
Begin installing available light fixtures in Classrooms A1-A6
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
AMI
- Pipe Fan Coil at 9C week of 1-17
- Awaiting valves for fan coils, delivery 1-17-22
Elens & Maichin ***Temps have been too cold to continue work***
- Fascia and Soffit framing on going in preparation for finish work
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
- Fascia blocking is on going
Week of 1/17/22 - 1/22/22
RB
May Decorating:
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
Smart Interiors
- Final taping in MPR
- Taping in corridors.
Consolidated
Regency Tile
- Start installing bathroom wall tile in classrooms A1-A8
Madden Glass
- Continue install of available windows & glass on going
- MPR window glass completed week of 12-27 ***minus entryways***
American
Begin installing available light fixtures in Classrooms A1-A6
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
AMI
- Pipe Fan Coil at 9C week of 1-17
- Awaiting valves for fan coils, delivery 1-17-22
Week of 1/24/22 - 1/29/22
RB
May Decorating
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
- Corridors on going
Smart Interiors
- Completing Taping in corridors.
- All other areas are completed
Madden Glass
- Classroom openings began 1-12
- Classroom openings are on going
- Corridor Entry units to begin
MEP
American
- Begin installing available light fixtures in Classrooms A1-A8
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
- Continue installing diffusers and Duct work
AMI
- Pipe Fan Coil at 9C week of 1-17, moved to 1-24
- Awaiting valves for fan coils, delivery 1-17-22
Elens & Maichin
- Fascia and Soffit framing on going in preparation for finish work
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
- Fascia blocking is on going
Week of 1/31/22 - 2/5/22
Consolidated
PSI
- Floor mitigation to begin in MPR and corridors. No access into building until 2-9-22 without prior coordination with Brian or Ian.
Regency Tile
- Tile on going in multi-use washrooms
- Complete grouting washrooms in classrooms Multi use washrooms
MEP
DeKalb
- 1 fan coil remains to be installed at corridor 9C
- Continue installing diffusers and Duct work
- Receive Radiant panels and install into grid.
AMI
- Pipe Fan Coil at 9C week of 1-17, moved to 1-24
- Awaiting valves for fan coils, delivery 1-17-22
- Tie in Radiant panels
Week of 2/7/22 - 2/12/22
Consolidated
- Begin installing VCT in MPR. ***Week of 2-14***
PSI
- Floor mitigation to begin in MPR and corridors. No access into building until 2-14-22 without prior coordination with Brian or Ian.
CSI
- Epoxy Floor finishes to begin in classroom washrooms A-1 thru A-8. No access into these washrooms until 2-14-22. Floors must be protected in order to do work in these spaces moving forward.
RB
- Frame out window benches in the classrooms, completing 2-7
- Carol Seating to complete final measurements for casework.
MEP
DeKalb
- Continue installing diffusers and Duct work
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
- Tie in Radiant panels. ***AMI completing remaining radiant panel tie ins in A-7, A-8 and Resource room, all other areas have been completed. ***
Week of 2/14/22 - 2/19/22
Week of 2/21/22 -2/26/22
Consolidated
- VCT on going in MPR.
- Classroom Carpeting install to begin following the ceiling tile installation.
MEP
DeKalb
- Cut in remaining diffusers
- Set remaining RTU, when available
AMI
- Complete any remaining valves for fan coils not yet completed
Jensen’s
- Plumbing fixture install on going.
Alpine Acoustics
- Complete any remaining grid work
- Begin installing ceiling tiles.
Week of 2/28/22 - 3/5/22
Consolidated
- Complete Carpet installs in classrooms
- Tile to be completed
CSI
- Waiting on materials to arrive to get work started.
RB
- Ceiling Grid and ceiling pads install
E&M
- Fascia and soffit install on going
- Wall panels to begin
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Week of 3/7/22 - 3/12/22
Consolidated
- Complete VCT in corridors
- Epoxy Floors on going (Pending material availability)
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Jensens
- Receive plumbing fixtures
- Begin installing plumbing fixtures
Week of 3/14/22 - 3/19/22
Consolidated
- Complete VCT in corridors
- Epoxy Floors on going (Pending material availability)
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Jensens
- Receive plumbing fixtures
- Begin installing plumbing fixtures
Week of 3/21/22 - 3/26/22
N/A
- Relocate construction office to resource room
E&M
- Finishing tie-ins and roof flashing/patching
Consolidated
- Finished up flooring in corridors and rooms 95%
Carol seating
- Will be out mid-week to deliver and start installing case work
Alpine
- Ceiling grid 95% complete
Jensen
- Continued work on installing plumbing fixtures
Hygineneering
- Abetment is on going
Week of 3/28/22 - 4/2/22
Week of 4/4/22 - 4/9/22
Madden Glass
- Finish installing SF Threshold
- Finish setting last of SF units in MPR
Consolidated
- Finish patch-in work in the classrooms and finish base (95%)
Jensen
- Continue installing plumbing fixtures
Reimer
- Start surveying for site work to commence
Oleson
- Start draining lake Henking and investigate remaining structure
Week of 4/11/22 - 4/16/22
Week of 5/2/22 - 5/7/22
Madden glass
- Finish store fronts
Consolidated
- Finish flooring in MPR, finish base (95%)
Jensen
- Finish tying in down spots
Reimer
- Site grading on West side and South side to continue
Oleson
- Waiting for decision on Lake Henking with new manhole and pipe work.
American Electric
- Start to trim classrooms. Change switch plates to stainless steel.
Eagle
- Frame sidewalks, stairs. Stone and pour concrete. East, West, and South.
Eilens & Maichin
- Finish facia and gutters
Week of 5/9/22 - 5/14/22
Week of 5/16/22 - 5/21/22
Madden Glass
- Finish two windows in MPR
Reimer
- Site grading on West side and South side to continue. Start filling in black dirt.
Eagle
- Frame sidewalks and pour south side
Elens & Maichin
- Finish facia and gutters and screens.
K & L
- Pave West side playground. Stone and prep east side on top of storm trap.
Action Fence
- Layout and install fence.
Seibert
- Start planting trees shrubs and laying sod west side.
Week of 5/23/22 - 5/28/22
Week of 5/31/22 - 6/4/22
Madden glass
- Finish two windows in MPR
Reimer
- Site grading on West side and South side to continue. Start filling in black dirt.
Eagle
- Frame sidewalks and pour south side.
Eilens & Maichin
- Finish facia and gutters and screens.
Action Fence
- Layout and install fence.
Seibert
- Start planting trees shrubs and laying sod west side.
American Electric
- Start to disconnect power in rooms and install temp lighting for demo.
Jensen Plumbing
- Disconnect bathroom fixtures for demolition. Start classroom disconnects.
DeKalb
- Drain HVAC system 6/2
AMI
- Drain HVAC system 6/2
Johler
- Start demo of rooms 11 & 13
Movers
- Move furniture in classrooms.
Week of 6/6/22 - 6/11/22
Lyon Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week of 12/13/21 - 12/18/21
- Week of 12/20/21 - 12/25/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/21/22 - 2/26/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 - 3/12/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 - 4/23/22
- Week of 4/25/22 - 4/30/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Week of 7/19/21 - 7/24/21
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Week of 8/16/21 - 8/21/21
Week of 8/23/21 - 8/28/21
Cibulka
- Prep/pour SOG
Albrecht
- Temp seed black dirt pile
- Work with AH on hauling spoils for trap
M/I
- Taking delivery on the 26th of deck and joists, will get started on the following Monday
Carey
- UG electric will wrap up
AJ
- Storm trap to start being excavated
- Existing downspout connections
- Tie in storm outside building
Week of 8/30/21 - 9/4/21
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
AJ
- Set storm trap on Friday the 17th
- Tie in the storm from building so can backfill
M/I Steel
- Will finish decking on end of day Wednesday
Doherty
- Start snapping lines and framing CFMF. Exterior delivery Monday morning start framing Tuesday
- Compass will be out Monday morning to layout
Jensen's
- Layout alongside Doherty-make sure pipes are in walls
- Set RD's starting Wednesday the 15th
FE MORAN
- Curbs to be set on deck starting the 15th
Cibulka
- Need to patch back sidewalk on NW side (school needs walking path back)
- Pour strom trap base on Wednesday
- Pour MPR slab on Friday
Albrecht
- Stone for MPR on Tuesday
Sebert
- Install SOD where sanitary line went in
Spancrete/Continental
- Will be onside Monday to remove the bracing in the MPR
Week of 9/20/21 - 9/25/21
Doherty
- Continue framing walls
Cibulka
- Finish pouring misc. sections of SOG
Carey
- Start layout ad establishing runs
Jensen's
- Working on setting/connecting RD's and layout
FE Moran
- Setting curbs, portals whatever is needed before roof insulation starts
- Confirmed per RFI 33 that pip supports will lay on top of insulation
AJ
- Storm trap date pushed to be set 9/23 (Thursday)
Spancrete
- Fix splice detail around perimeter of precast any day after Tuesday
- Patch holes from bracing
Week of 9/27/21 - 10/2/21
AJ
- Will finish strom trap, backfilling and connecting pipes at each end
- TIe in storm on east side
- Downspout connections in courtyard approved
M/I
- Missed bent angle above windows needs to be installed
Spancrete
- Fix splice detail around perimeter of precast
- Patch holds from bracing
Doherty
- Continue framing and start sheathing exterior walls for mason to get started
- IWS to spray fluid applied air barrier
Hargrave
- Delivery of frames
FE MORAN/AMBER
- 9/30 curbs to show up and be installed
Jensen's
- Start rough
Week of 10/4/21 - 10/9/21
Week of 10/11/21 - 10/16/21
DCG/Alloy/Filotto
- Wood blocking for lower roofs
- Kettle set up on east haul road and crane in courtyard
- Flashing to start on roof walls
- Wrap up the MPR roof this week
- Filotto to get rolling on temping in both shingled roofs
AMBER
- Keep working on handing ductwork
- Curb work
Doherty
- Keep on framing - interior and exterior walls/dormers on north elevation
- Sheathing, air barrier and rigid insulation ongoing
Jensen's
- Rough plumbing
Hargrave
- Once an answer on spray foam then grames can be set
Carey
- Rough Electric
FE Moran
- Working hand in hand with Amber on curbs
- Layout boiler room - access on 10/15. No school day
Nelson FP
- Will start FP pipe in MPR
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
Albrecht
- Stone southside
- Temp seed dirt pile on south
M/I
- Bent angles for above windows (RFI 43)
- Angle at vest 101
Mastership
- Mobilize by end of week
Week of 10/18/21 - 10/23/21
DCG/Alloy/Filotto
- Wood blocking for lower roofs
- Flashing to start on roof walls after iWS
- Filotto to get rolling on temping in both shingled roofs per RFI 44 on Monday
- DCG to continue lower flat roofs
- Build dividers
Amber
- Keep working on ductwork
Doherty
- Keep on framing interior walls
- Sheathing, ongoing on north elevation
- IWS needs to keep going on air barrier (weather)
Jensen's
- Rough plumbing
Hargrave
- Will be setting door frames and start to temp up openings
Carey
- Rough electric
FE Moran
- Continue layout and piping
Nelson FP
- Rough FP
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
M/I
- Bent angles to be installed in all eight locations on Tuesday
Mastership
- Mobilize by end of week
Week of 10/25/21 - 10/30/21
DCG/Alloy/Filotto
- Wood blocking
- Cap sheet
- Install skylights
- Filotto to keep working on shingled roofs
Amber
- Keep working on hanging ductwork
- DOAS UNITS TO BE ONSITE WITH CRANE ON THURSDAY (10/28)
- Get drops set inside RTU's
Doherty
- IWS to continue work with air barrier
- Insulation and frame for inside of DOAS units
- Start framing walls at gulley of roof for wall panels
Jensen's
- Rough plumbing
- Set hose bibs before brick starts
Hargrave
- Will be setting door frames
- Start to temp up exterior openings
Carey
- Rough electric
FE Moran
- Continue layout and piping
- Investigate work inside existing boiler room
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
M/I
- Maybe one day to finish up decking dormers and clean up
Mastership
- Start mobilizing on Tuesday
Week of 11/1/21 - 11/6/21
DCG/Alloy/Filotto
- Cap sheet
- Install skylights
- Filotto to keep working on shingled roofs
AMBER
- Keep working on hanging ductwork
- DOAS units were set on Friday
Doherty
- IWS to continue work with air barrier
- Start framing walls at gulley of roof for wall panels
- Frame soffits along exterior
Jensen's
- Rough plumbing
- Set hose bibs before brick starts
Hargrave
- Temp up exterior openings with plywood and plastic
Carey
- Rough electric
FE Moran
- Prep for temp heat
- Roughing
AJ Oleson
- Set structures on top of storm trap
- Backfill storm line connect on east
M/I
- Supply lintels for brick
Mastership
- Start in courtyard
Week of 11/8/21 - 11/13/21
DCG/Alloy/Filotto
- Alloy metal wall panels
- Z-flashing along perimeter
- Filotto working on shingles
AMBER
- Ductwork should be wrapping up
Mastership
- Courtyard brick and stone sills
Doherty
- Air barrier work
- Insulation of walls once watertight (should be this week)
Jensen's
- Plumbing rough
Carey
- Electric rough
FE Moran
- Rough piping continue
Week of 11/15/21 - 11/20/21
DCG/Alloy/Filotto
- Flashing and coping work will be ongoing
- Shingles will continue
Mastership
- Face brick in courtyard
- M/I supposed to deliver lintels this week
Doherty
- Insulation of interior and exterior walls once roof if watertight
MEPFP's
- Continue roughing maybe start looking to get in wall inspections
AJ
- Once brick is far enough along in VY then we can connect downspouts
Week of 11/22/21 - 11/27/21
DCG/Alloy/Filotto
- Filotto to start installing shingles
- Wood blocking and fascia plywood
- NW corner
- Skylights and roof hatches
Doherty
- Start skylight framing
- Bench framing once spray foam is far enough along
- Drywall start by end of month
- Spray foam ongoing
- Backing in classrooms
AMBER
- Ductwork and hanging fan coils
Jensen's
- In-wall water piping
- Flush valve/rab bar dilemma
Carey
- Rough electric
- Subs got started
FE Moran
- Rough piping
- Cap curb with no unit
- Welding gas pipe on roof
- Temp control guy to get started sooner than later
M/I
- Splice detail per $3.00 detail 5
Mastership
- Working on brick in courtyard
- CMU walls in MPR on rain days
Week of 11/29/21 - 12/4/21
In wall inspections before drywall
DCG/Alloy/Filotto
- Alloy metal wall panels
- Filotto should be close to complete
AMBER
- Mech rough almost complete
Mastership
- Courtyard brick and stone sills to starts
Doherty
- Insulation of walls
- Spray foam almost complete
- Skylight framing
- Drywall uppers
Nelson
- Once skylight framing is complete Nelson will get back onsite
Jensen's
- In wall water piping
Carey
- Electric rough
FE Moran
- Roughing
Week of 12/6/21 - 12/11/21
DCG/Alloy/Filotto
- Filotto ongoing work with shingles
- DCG to fix NW corner
- Skylights and Roof hatches
- Set RD Covers
Doherty
- Skylight framing
- Drywall starts Tuesday
- Sheath dormer side walls for roofer
- In-wall insulation
AMBER
- Hanging fan coils
Jensen’s
- In-wall water piping
- Insulating water pipe
- Air testing
Carey
- Rough Electric
FE Moran
- Rough gas piping
- Welding gas pipe on roof
- Temp control guy to get started
M/I
- Splice detail per S3.00 detail 5
- Lintel at East end to be installed
Mastership – complete in 2 weeks
- Working on brick on north elevation
- Stone sills being installed
- Brick wash in courtyard
- NEED FRP DOORS-Hargrave
- CMU walls in MPR on rain days
AJ Oleson
- Start on courtyard downspout connections(3/4 days)
Maddon Glass
- Get started working behind the brick washer installing frames/glass by end of week or early next
Hargrave
- May have to take some temp board up down, but I will confirm once I know.
Week of 12/13/21 - 12/18/21
DCG/Filotto/Alloy
- Alloy metal wall panels
- Filotto should be almost 100%
Maddon Glass
- Start setting frames/glass in courtyard behind the brick washer
Amber
- Mech Rough Overhead
Mastership
- Brick on east elevation
- Brick washer
Doherty
- Insulation of walls
- Drywall
Nelson
- Once Skylight framing is complete Nelson will get back onsite
Jensen’s
- Rough Plumbing
Carey
- Electric Rough
FE Moran
- Roughing Overhead
Week of 12/20/21 - 12/25/21
Week of 1/10/22 - 1/15/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed sooner than later above storefronts
Doherty
- Drywall/Durarock
- Taping/Sanding
- Insulation
- Paint Mockup
- Painter to start priming Monday
Hargrave
- Board up down Tuesday on North elevation
AMBER
- Move FCU’s in ELEC room and Resource room 116B ASAP -have answers
Jensen’s
- Overhead Rough
- Pipe Insulation
- Overflows in MPR to exterior
NELSON
- When looking for Inspection?
Carey
- Rough Electric Overhead
- NW corner rough
- Fire Alarm sub to start
FE Moran
- Piping to each fan coil unit
- Finish gas run into existing school at NW corner
Mastership
- Clean CMU prior to paint
- FRP doors holding up NW corner
- SF-L4 east end add more brick
- Waiting on confirmation date for sills
AJ Oleson
- Start on courtyard downspout connections (3/4days)
Maddon Glass
- Frames/Glass being installed northside
Week of 1/17/22 - 1/22/22
DCG/Filotto/Alloy
- Alloy metal wall panels to start weather dependent
Consolidated/Regency
- Should stop out this week to look
Maddon Glass
- Should be wrapping up end of week
Doherty
- Painting
- Durarock in bathrooms
- Drywall skylights
- Taping. /Mudding/ Sanding
- Alpine to start on grid in bathrooms
Jensen’s
- Rough Plumbing Overhead
Carey
- Electric Rough Overhead
FE Moran
- Roughing Overhead
Week of 1/24/22 - 1/29/22
**ALL trades to start fire caulking/sound caulking
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed sooner than later above storefronts
Doherty
- Taping/Sanding/Mudding
- Painting
- Grid in classrooms (no secure to deck)
Consolidated
- Tile ongoing in bathrooms
AMBER
- Waiting for more grid to go up to start setting registers etc.
- Fire caulking penetrations
Jensen’s
- Overhead Rough
- Pipe Insulation ahead of grid
- Pipe labeling
- Fire/sound caulking
NELSON
- Start Fire caulking
- Remove labels off pipe in 3 rooms before paint (Painting end of week)
Carey
- Rough Electric Overhead
- MPR Rough to start back up after FA
FE Moran
- Condensate lines finish and insulate to FCU’s
- Prep for radiant ceiling tiles
- Finish run to NW corner
- Insulation of pipe
Mastership
- FRP doors holding up NW corner
- SF-L4 east end add more brick
- Waiting on confirmation date for sills
Maddon Glass
- Frames/Glass being caulked exterior and interior
Week of 1/31/22 - 2/5/22
DCG/Filotto/Alloy
- Wall panels once weather turns
Consolidated/Regency
- Tile in bathrooms
Doherty
- Painting MPR this week
- Sanding/Taping
- Alpine working on grid to move into classrooms
Nelson
- Start setting heads in grid behind the grid
Jensen’s
- Rough plumbing overhead
Carey
- Electric rough overhead
FE Moran/Amber
- Roughing overhead
- Ready for duct sock install end of week
Week of 2/7/22 - 2/12/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed above storefronts
Doherty
- Taping/Sanding/Mudding almost wrapped up
- 1 day left to complete the paint in MPR
- Grid in corridors starting
- Skids of ceiling tiles being delivered
Consolidated
- Tile ongoing in bathrooms
- Waiting on purple tile
AMBER
- Fire caulking penetrations
- Setting registers in grid
Jensen’s
- Pipe Insulation
- Pipe labeling
- Fire/sound caulking
NELSON
- Setting heads in grid
Carey
- Lights delivery Monday
- Overhead rough
FE Moran
- Condensate lines finish and insulate to FCU’s
- Water on hot water pumps
- Hanging CAB units
- Insulation of pipe ongoing
Mastership
- SF-L4 east end add more brick
- Brick by FRP doors on hold
- Waiting on confirmation date for sills
Maddon Glass
- Frames/Glass being caulked exterior and interior
- Waiting on me for SF-L4 I need to pour more concrete
Week of 2/14/22 - 2/19/22
DCG/Filotto/Alloy
- Wall panels once weather turns
Consolidated/Regency
- Tile in bathrooms
Doherty
- Painting
- Alpine working on grid and hangers for lights
Nelson
- Setting heads
Jensen’s
- Rough Plumbing Overhead
Carey
- Electric Rough Overhead
FE Moran/Amber
- Roughing Overhead
- Ready for duct sock install end of week
Week of 2/21/22 - 2/26/22
Week of 2/28/22 - 3/5/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed above storefronts
Doherty/Alpine
- Start dropping ceiling tiles once IMEG punch list is complete hopefully middle of week
NELSON
- FSCI is on the schedule for today 2-28
Carey
- Lights install
- Runs to electric room in existing school
- Working towards perm power over spring break
FE Moran
- Waiting on 6 correct valves to be delivered
MEPFP Overhead
- Inspections in classrooms and bathrooms passed
- Hallways/MPR/resource rooms to still be inspected
Mastership
- SF-L4 east end add more brick
- Brick by FRP doors
- Sill work
Maddon Glass
- Need doors for Curtain Walls
- Waiting on concrete stoop for SF-L4
- Other 2 window openings (SE corner tie in) won’t be until summer until we can demo the old
Week of 3/7/22 - 3/12/22
Week of 3/14/22 - 3/19/22
Week of 3/21/22 - 3/26/22
Consolidated
- Epoxy will finish this week
- Carpet and VCT should finish this week
Cibulka
- Look to start pouring stoops
AJ Oleson
- Water service work and maybe downspout work in courtyard
Carey
- ComEd
- Work on perm power for addition
Hargrave
- Cabinet /FEC’s/Toilet Accessories to deliver this week sometime
- Start install where is ready
Jensen’s
- Plumbing fixture delivery
Week of 4/4/22 - 4/9/22
DCG/Alloy/Filotto
- Coping/Gutters ongoing
- Wall Panels
- Plywood for coping installed above storefronts
M/I
- Out to install roof ladders
AJ
- Downspouts so we can start grading/pouring concrete
- Manholes covers to set everywhere
Albrecht/Cibulka
- Start second half of the week on grading
Doherty/Five Star
- Doherty to fix by grille for amber in storage room
Carey
- Trim work and disconnect trailer (Trailer picked up on 7th morning)
FE Moran
- RTU 1
Maddon Glass
- Interior glass for doors
- Caulk exterior Curtain Walls
- Waiting on me for SF-L4 I need to pour more concrete
- Other 2 window openings (SE corner tie in) won’t be until summer until we can demo the old
Hargrave
- Casework/cabinet Install
- Solid surface install
- Bathroom partition install
- FEC’s
Week of 4/11/22 - 4/16/22
Cibulka
- Start pouring stoops, walks, curbs
Hargrave
- Cabinet /FEC’s/Toilet Accessories
- Bathrooms partitions
- Solid surfacing
Jensen’s
- Once enough classroom cabinets are installed then get back out to start installing sinks
DCG/ALLOY
- Working on coping
Albrecht
- Grading
Maddon
- Set SF-L4 when concrete poured
Consolidated
- End of week beginning of next finish up base everywhere when cabinets complete
Week of 4/18/22 - 4/23/22
DCG/Alloy/Filotto
- Coping/Gutters
- Overflows to get tightened
Albrecht/Cibulka
- Working in courtyard on walks/curbs
- Albrecht grading and bringing stone in
Doherty/Five Star
- Doherty to fix by grille for amber in storage room
- Stencil fire rated wall at NW corner
- Frame chase at East Storefront-setting storefront Monday-should be ready to start framing Wednesday
Jensen’s
- Setting sinks in classrooms
- Downspouts
FE Moran
- JCI looking to start up FCU’s and setting thermostats
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Interior glass for doors early in week
- Caulk exterior Curtain Walls
- SF-L4
Hargrave
- Wood doors and hardware to show up Tuesday
- Solid surface install
- Bathroom accessories ongoing
- FEC’s
- Kitchen Equipment
Consolidated
- Base
- Get epoxy material picked up
Week of 4/25/22 - 4/30/22
Week of 5/2/22 - 5/7/22
DCG/Alloy/Filotto
- Coping/Gutters
- 8 existing downspouts to get reworked
- Insulated Wall Panels
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka
- Working in courtyard on walks/curbs
- Albrecht grading up north and east
- Walks to start on north this week
- Meeting onsite for Courtyard (SEBERT/PLAYGROUND EQUIP)
Doherty/Five Star
- Stencil fire rated wall at NW corner
- Paint cast iron for downspouts to match the aged bronze
- Water fountain at NW the grey paint needs to wrap the bump outs
- Tape new chase built and grille patches
- Patch dings and paint touch up prior to the main Punchlist
Carey
- Exterior lights
- Applied/First Security missing some covers
- Panel schedules
- Horns in MPR to move
FE Moran
- JCI working on FCU’s and setting thermostats
- Covers for thermostats- JCI
- Looking to get gas to DOAS units
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Caulk exterior Curtain Walls
Hargrave
- Wood doors and hardware to start
- FEC’s
- Grab bars
Week of 5/9/22 - 5/14/22
Cibulka/Albrecht/Sebert
- Cont. pouring stoops, walks, curbs
- Grading
- Playground Equipment should be onsite
- Landscaping to start and rubber surfacing post equipment
Doherty/Five Star/Alpine
- Grid to fix
- Make a few T’s removable for access to filters
- A lot of paint to touch up and just finish
FE Moran
- Gas to DOAS
Hargrave
- Wood doors
- Hardware
- GYM EQUIP
- Marker boards and tack boards this week
DCG/ALLOY
- Finish up coping and wait for insulated wall panels
Consolidated
- Finish VCT after FRP frames/doors are in
- Sealed concrete in JCI
Week of 5/16/22 - 5/21/22
DCG/Alloy/Filotto
- Coping/Gutters
- 8 existing downspouts to get reworked
- Insulated Wall Panels
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka/Sebert
- Working in courtyard landscaping
- Playground equipment
- Albrecht waiting on Cibulka so they can start spreading black for Sebert
- Walks to start on north
Doherty/Five Star
- Stencil fire rated wall at NW corner
- EM Seal after patch work
- Paint cast iron for downspouts to match the aged bronze
- Paint Precast
- Water fountain at NW the grey paint needs to wrap the bump outs
- Tape new chase built and grille patches
- Patch dings and paint touch up prior to the main Punchlist
- Returns after FRP frames are in
Mastership
- Send someone to recess the FEC missed in MPR
Consolidated
- Sealed concrete in JC
Carey
- Exterior lights
- Roller shades
- Horns in MPR to move
FE Moran
- JCI working on start up
- thermostats-
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Caulk exterior Curtain Walls
Hargrave
- Ram board clean up before cleaners
- Doors and hardware
- FEC’s
- Grab bars
- Wood infill to match existing at NW tie in
Nelsons
- Set all heads flush with ceiling tile
Week of 5/23/22 - 5/28/22
Cibulka/Albrecht/Sebert
- Cont. pouring stoops, walks, curbs
- Grading
- Playground Equipment should be onsite
- Landscaping to start and rubber surfacing post equipment
Doherty/Five Star/Alpine
- Grid to fix
- Make a few T’s removable for access to filters
- A lot of paint to touch up and just finish
Carey
- Downspout melt system
- Hoops when arrive
Hargrave
- Cleaners Monday
- FRP to show up
- Hardware
- GYM EQUIP
- Marker boards and tack boards
DCG/ALLOY
- Insulated wall panels
Consolidated
- Finish VCT after FRP frames/doors are in
Week of 5/31/22 - 6/4/22
DCG/Alloy
- 8 existing downspouts to get reworked
- Insulated Wall Panels when delivered
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka/Sebert
- Rubber surfacing to start
- Walks on north side
Doherty/Five Star
- Stencil fire rated wall at NW corner
- Grid to be fixed/make some removable Ts for access to filters
- EM Seal after patch work
- Water fountain at NW the grey paint needs to wrap the bump outs
- Returns after FRP frames are in
Carey
- Exterior lights
- Roller shades
- Cages in MPR
- Snow Melt system-Gutters are complete
- Horns in MPR to move
FE Moran
- RTU to be set soon
Maddon Glass
- Caulk exterior Curtain Walls
Consolidated
- Finish VCT after FRP frames/doors are in -will follow up
Hargrave
- FRP
- Marker boards tack boards
- Grab bars
- Wood infill to match existing at NW tie in
- Basketball hoops
Nelsons
- Set all heads flush with ceiling tile
Springman Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week of 12/13/21 - 12/18/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/28/22 - 3/4/22
- Week of 3/7/22 - 3/11/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 - 4/2/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 - 4/23/22
- Week of 4/25/22 - 4/30/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week 6/6/22 - 6/11/22
- Week of 6/13/22 - 6/18/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Albrecht
- Finish backfill + stone at area G
- Dig fluid cooler pad
- finish haul road to trailer
Eagle
- Pour storm trap
- Pour fluid cooler pad
AJ Oleson
- Finish sanitary piping and structures
- Locate and pick up existing piping in courtyard area to complete fluid cooler pad
- Pour fluid cooler pad
Johler
- Finish concrete demo at South Gymnasium
Jensen
- Start underground in science addition
- Complete any re-piping at area D/F to mechanical room
Carey Electric
- Finish reconnect mechanical room panel
- 220v for mason
- Disconnect CUV at rooms
FE Moran
- Reconnect piping at mechanical room
- CUV relocation
DCG
- Finish any temp roofing at gymnasium to keep existing watertight
Week of 7/19/21 - 7/24/21
Albrecht
- Start pad/excavate at gymnasium
- Slab stone at Area G with UG plumbing is complete
AJ Oleson
- Locate and pick up existing piping in courtyard area to complete fluid cooler pad
Johler
- Demo at overhang area G/E
Jensen
- Finish underground in science addition
- Complete any re-piping at area D/F to mechanical room
Carey Electric
- 220v for mason
- Work with mason at interior wall starter course (if needed)
FE Moran
- Reconnect piping at mechanical room
- CUV relocation
- Fluid cooler pad
Mastership
- Start interior wall starter course below slab (when plumbing is complete)
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Albrecht
- Backfill at gymnasium
- Crane pad for spancrete
Eagle
- F/R/P footings at gymnasium
AJ Oleson
- Reconnect any existing lines needed
Carey Electric
- CMU rough
FE Moran
- Duct layout and thermostat rough with mason as needed
Mastership
- Exterior/interior walls
Hargrave
- Window protection
Jensens
- Complete pit and ug rough for existing lines in area F
- In wall rough in area G
Week of 8/16/21 - 8/21/21
Albrecht
- Backfill at gymnasium
- Stone at pad
Eagle
- Finish all frame/reinforce/pour (F/R/P) footings at gymnasium
AJ Oleson
- Reconnect any existing storm lines
Carey Electric
- CMU rough at Area G
FE Moran
- Thermostat / control rough with mason, as needed
Mastership
- Finish first floor walls and stairwells at Area G
Jensen's
- In wall rough in area G
Spancrete
- Dead men install
- Start precast install at Area F
Week of 8/23/21 - 8/28/21
Week of 8/30/21 - 9/4/21
Albrecht
- Stone at Area F pad
Eagle
- Frame pour area of wall after gas line relocation
AJ Oleson
- Reconnect any existing storm lines
Carey Electric
- CMU wall rough at Area G/F
FE Moran
- Thermostat/control rough with mason as needed
Mastership
- First floor load bearing walls at Area F
Jensens
- In wall rough at Area G
Spancrete
- Grout panels
M&I
- Start second floor steel and deck at Area G
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Albrecht
- Stone at Area F pad
Eagle
- Pour at 2nd floor deck at Area G 9/14
Carey Electric
- CMU rough at Area G/F
FE Moran
- Thermostat / Control rough with mason as needed
Mastership
- Finish load bearing walls at Area F
- Second floor walls at Area G
- Fluid applied air barrier at Area G
- Mock-up
Jensens
- In wall rough at Area G
Spancrete
- Finish caulking panels
M&I
- Lower roof framing at Area F
Hargrave
- Safety rails and temp stairs at Area G, second floor, 9/13
Week of 9/20/21 - 9/25/21
Week of 9/27/21 - 10/2/21
Carey Electric
- CMU wall rough at Area G/F
FE Moran
- Thermoset / Control rough with mason, as needed
Mastership
- Finish face brick at North wall Area F
- Bearing walls at Area F
- Face brick at Area G
Jensens
- Chase wall rough at Area G
- UG at Area F
- Roof drains at Area F
Spancrete
- Finish caulking brick panels
- Remove structural supports 10/28 AM
M&I
- Finish lower roof framing and deck at Area F
- Finish gym roof framing and deck
- Start Area G roof framing
Albrecht
- Backfill at Northwest corner of Area F
- Stockpile stone in Area F after M&I equipment is out
- Stone areas of pad after UF plumbing is complete and prepare for electrical UG
Week of 10/4/21 - 10/9/21
Mastership
- Finish face brick at Area G
- All bearing walls at Area F need to be complete and read for steel install by 10/5
Johler/Hargrave
- Demo at front company
Carey Electric
- CMU walls rough at Area G/F
- UG at Area F
FE Moran
- Thermostat/Control rough with mason, as needed
- Ductwork install at Area G first floor
Jensen's
- UG at Area F
M&I
- Finish steel frame at Area F lobby before epic deck arrives on 10/11
- Finish roof framing and decking at Area G
Doherty
- CFMF at Area F soffits
Spancrete
- Install leave out panels
Albrecht
- Stone remainder of pad in Area F
Week of 10/11/21 - 10/16/21
Carey Electric
- CMU rough at Area G/F
- UG at Area F
FE Moran/Amber
- Duct work at first floor Area G
- Roof cubs install
- Gas line take offs
Mastership
- Face brick at Area G/F
- Demo and patch at existing - T&M RFP-014SP
Jensen's
- UG at Area F
- Roof drains at Area F/G
Spancrete
- Finish caulking brick panels (caulk color has been approved)
- Remove wall bracing after roof
M&I
- Finish gym roof deck
- Epic deck at lobby
Albrecht
- Stone remainder at Area F pad
- Haul out spoils and dress up Haul Road
Doherty
- CFMF soggits at Area G/F
DCG
- Start roof blocking at available areas (coordinate with Doherty)
Eagle
- Prep/pour SOG at east and south elevations of F (Thursday-Friday)
Week of 10/18/21 - 10/23/21
Carey Electric
- CMU rough at Area G/F
- UG at Area F lobby and gym
FE Moran/Amber
- Finish ductwork at first floor Area G
- Roof curb install
- Gas lines
Mastership
- Face brick at Area G/F
- Demo and patch at existing
- Brick wash
Jensen's
- DWV
- Roof drains at Area F/G
M&I
- Stairs in south tower Area G
Albrecht
- Stone remainder of pad in Area F
Doherty
- Finish CFMF soffits at Area G/F
DCG
- Start roof blocking at available areas (coordinate with Doherty)
Eagle
- Prep/pour SOG at all available sections
Hargrave
- Board up at all locations
Nelson
- FP pipe install at Area G, first floor
Week of 10/25/21 - 10/30/21
Carey Electric
- Any in wall rough with mason
FE Moran/Amber
- Set RTU
- Temp heat rough in
Mastership
- Finish front entry
- Finish face brick at elevations that have roof blocking and vapor barrier completed
- Demo and patch at existing
- Brick wash at all available locations
Jensen's
- DWV
- Roof drains at Area F/G
- Storm line at Fluid coolers (to be coordinated by N&A)
M&I
- Stairs in north tower Area G
- Front canopy
Doherty
- Finish CFMF soffits at Area F
- Start CFMF at storefront locations Area F
DCG
- All roof blocking to be complete
- Install stainless steel flashing at roof blocking
- Material delivery
- Start Area G roof
Eagle
- Prep/pour SOG at remaining locations
- Prep/pour south stairwell at Area G
- Doweling at Area F interior walls
Hargrave
- Finish board up at all locations
Week of 11/1/21 - 11/6/21
Carey Electric
- Any in wall rough with mason Area F interior walls
FE Moran/Amber
- Temp heat rough in
- Coordinate any masonry openings in Area F
Mastership
- Finish face brick at elevations that have roof blocking and vapor barrier completed
- Demo and patch at existing
- Brick wash at all available
- Interior walls at Area F
Jensen's
- DWV
- Roof drains at Area F
- Storm line at fluid coolers (to be coordinated by N&A)
M&I
- Canopy at front entry
Doherty
- Finish CFMF soffits at Area F
- Start CFMF at storefront locations Area F
- Vapor barrier at Area G soffits
DCG
- All roof clocking to be complete
- Finish area G roof
- Start gym roof
Eagle
- Pour missing foundation at existing
- Prep/pour North and South stairwell at Area G
- Doweling at Area F interior walls
Hargrave
- Finish Board up at all locations
Madden
- Start CW install at Area G
Week of 11/8/21 - 11/13/21
Week of 11/15/21 - 11/20/21
Week of 11/22/21 - 11/27/21
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in at gymnasium
FE Moran/Amber
- Set RTU in Area G
- Cut wall openings at second floor Area G
- Second floor duct work
- Finish all chase wall rough at Area G
Mastership
- Finish all brick wash
- Interior walls @ Area F
Jensen’s
- DWV
- In wall rough as needed @ Area F
- Finish Area G Chase wall rough and have inspected
Doherty
- Start Roof top unit detail as described in M3.00 SP***
- Start firring for Tectum in Area G***
- Frame Interior soffits and bulkheads @ Area G
- Finish all storefront CFMF in Area F
DCG
- Finish West and North lower roofs @ Area F
- Start Tie in @ Existing
- Field Measure for insulated Panels in available locations***
- Coping @ all available ***
Hargrave
- Finish Area G/F door frames***
Madden
- CW install @ Area G
- S/F install @ Area F
- Glass install @ all available
Week of 11/29/21 - 12/4/21
Mastership
- Finish interior walls @ Area F
- Chase walls @ Area G
Carey
- CMU Rough with Mason
- Rough in @ Gymnasium
Jensen’s
- DWV
- CMU Rough with Mason
Doherty
- Frame interior soffits and bulkheads
- Roof top unit detail @ area F
- Tectum panel install
- Spray insulation @ Area F
DCG
- Tie- in @ all existing/new
- Insulated Metal panel/ coping install
Week of 12/6/21 - 12/11/21
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in @ Gymnasium
FE Moran/Amber
- Set RTU in Area G (Please confirm exact date) *** ***
- Cut wall openings @ 2nd Floor Area G *** ***
- 2nd floor duct work ***
- Finish all Chase wall rough @ area G ***
- Start Gymnasium Ductwork
Mastership
- Finish all brick wash *** ***
- Interior walls @ Area F North locker rooms ***
- Start/ Finish Chase walls @ Area G
Jensen’s
- DWV
- Coring @ Gymnasium
- Finish storm drain Tie in
- Chase wall rough @ south locker room Area F
Doherty
- Roof top unit detail as described in M3.00 SP
- Tectum install @ Area G 2nd floor ***
- Frame Interior soffits and bulkheads @ Area G *** ***
- Finish bulkhead at Interior storefront front entry
- Finish all waterproofing and insulation ***
DCG
- Field Measure for insulated Panels in available locations*** ***
- Coping/ insulated panels @ all available *** ***
Hargrave
- Finish Area G/F door frames***
Madden
- S/F install @ Area F
- Glass install @ all available
Nelson
- FP piping @ 1st floor science rooms
- FP piping @ Gymnasium
Week of 12/13/21 - 12/18/21
Mastership
- Finish interior walls @ Area F ***
- Finish Chase walls @ Area G
- Chase walls @ South Locker rooms
Carey
- CMU Rough with Mason
- Rough in @ Area F
Jensen’s
- Chase wall Rough @ North locker rooms
- CMU Rough with Mason
Doherty
- Frame interior soffits and bulkheads
DCG
- Insulated Metal panel/ coping install
Nelson
- FP piping @ 2nd floor science rooms
Week of 1/10/22 - 1/15/22
All Trades
- Last chance to get all material and garbage out of area G before paint starts
- All work prior to paint should have been done last week
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in @ Gymnasium
- LV rough in Area F
- Rough @ North Lobby Soffits
FE Moran/Amber
- Duct work in Area F
- Duct @ North lobby soffits
Mastership
- Finish all walls in Area F except for chase walls at gym curtain
- Caulk exterior
- Finish all bullnose before paint
- Start rub down walls in area F
Jensen’s
- Supply rough @ Area F
- Pipe insulation @ Area F
Doherty
- Framing and drywall in stairwells
- Frame west lobby soffits
- Finish taping and sanding @ all Area G soffits
- Start Block fill @ 2nd floor Area G?
DCG
- Field Measure for insulated Panels in available locations*** *** *** *** *** ***
- Coping/ insulated panels @ all available *** *** *** *** *** ***
- Temp tie in at existing by front entry *** ***
- Pipe portal in gymnasium north end and for signage on west end *** ***
Hargrave
- Coordinate door frame installs with Mason for Area F
- Finish any previously installed frames complete (Bondo/caulk) *** ***
- Remove temp wall material and garbage
- Gymnasium curtain track install
- Framing @ casework chase locations
Madden
- Cover installs
- West vestibule S/F install
Nelson
- FP piping @ North lobby soffits
- FP piping at All remaining Area F
- All fire caulking complete in area G
Week of 1/17/22 - 1/22/22
Week of 1/24/22 - 1/29/22
All Trades
Carey Electric
- Rough in @ Area F
- LV rough in Area F
FE Moran/Amber
- Duct work in Area F
Mastership
- Prep walls for paint in Area F
- Chase walls @ Gym curtain soffit
- Interior Caulk @ Area F
Jensen’s
- Supply rough @ Area F
- Pipe insulation @ Area F
- Move storm piping @ gym soffit
Doherty
- Finish taping and sanding drywall @ stairwells
- Start framing Gym curtain soffit
- Framing @ Soffit RFP 014
- Finish painting Area G
DCG
- Field Measure for insulated Panels in available locations
- Coping/ insulated panels at all available
- Pipe portal in gymnasium north end and for signage on west end
Hargrave
- Finish installing any frames
- Caulk and Bondo Frames in Area F
- Remove all temp board up garbage from gym
Madden
- Finish all frame covers and sunshades
- Finish all exterior caulking
- East side of North lobby vestibule S/F install ***
Nelson
- All fire caulking complete in Area F
- Area F rough complete
Week of 1/31/22 - 2/5/22
Mastership
- Finish Gym curtain chase walls
- Finish interior Caulk at Area F
- Finish wall prep@ Area F
Carey
- Rough in at Area F
- LV rough at Area F
Jensen’s
- Supply rough in Area F
- Pipe insulation at Area F
Doherty
- Start Paint at Area F
- Tape Sand Drywall at Area F
DCG
- Insulated Metal panel / coping install
Moran/Amber
- Finish Area F ductwork / piping
Madden
- West lobby S/F install
Week of 2/7/22 - 2/12/22
All Trades
- Work on getting any materials out of Area G. Must be out for floor mitigation starting 2/17
Carey Electric
- Rough in @ Area F
- LV rough in Area F
- Electrical trim @ Area G
- Lighting @ Area G
FE Moran/Amber
- Finish All ductwork @ Area F
- Trim out @ Area G
Mastership
- All walls need to be prepped and ready for paint @ Area F
- Demobilize and clean up in Gymnasium
- Finish ALL Interior Caulk @ Area F
- Wash Brick @ North lobby
- Fire Caulk @ all Rated walls
Jensen’s
- All Pipe insulation to be complete
- Valve tags, stickers, fire caulk
Doherty
- Finish ceiling grid at Area G
- Finish Gym curtain soffit + taping and sanding complete
- Framing @ Soffit RFP 014
- Finish painting frames at Area G
- Block fill/Prime/ Paint at Area F Storage Area, West Lobby, North and South Locker rooms
DCG
- Coping/ insulated panels at all available
- Pipe portal in gymnasium north end and for signage on west end
Hargrave
- Finish prepping frames for paint
Madden
- Finish all frame covers and sunshades
- Finish all exterior caulking
- S/F install at West lobby
Nelson
- Measure heads at all drop ceiling locations at Area G (coordinate with N&A first to make sure grid is complete)
Week of 2/14/22 - 2/19/22
Week of 2/28/22 - 3/4/22
All Trades
- All Materials and Equipment needs to be removed from the Gymnasium by the end of this week
Carey Electric
- Pull Fire Alarm at Area F
- Install projector and screens after Gym ceiling is painted
- Pipe /wire electric heaters
- Light install at all available in Area F
- Re-pipe at Main entrance Doors for new Electric Strike Location
FE Moran/Amber
- Finish All ductwork at Area F
- Pull communication wire at Area F
- Install fabric duct in gym after ceiling is painted
- Install electric Heaters
- Install ceiling diffusers where available
Mastership
Jensens
Doherty
- Finish Wall Paint in Gymnasium ceiling + walls
- Finish taping soffit in North Lobby
- Ceiling grid in North locker rooms, PE offices, G 100 lobby/ vestibule, West Lobby and North Lobby
- Drywall at G118 Vestibule
DCG
- Start metal coping and flashing
Hargrave
- Madden
- Finish all caulking
- S/F install at West lobby
- Install Mull Extensions at Area G
- Finish Door Installs
Nelson
- Start Sprinkler head install at Area F Grid locations
- Move line at G 118 Vestibule
Consolidated/PSI
- Start VCT install at 2nd floor Area G
Week of 3/7/22 - 3/11/22
All Trades
- All Ceiling trim and above grid work needs to be completed in locker rooms by the end of this week
Mastership
Carey
- Electrical Trim at any Area F painted locations and ceiling grid locations
Doherty
- Ceiling grid complete by 3/8
DCG
- Coping /Flashing install
Moran/Amber
- Trim at any ceiling grid locations
Madden
Nelson
Consolidated
- Finish 2nd floor VCT Install
- Start 1st floor VCT Install
- Start Gymnasium Floor Mitigation
Week of 3/14/22 - 3/19/22
All Trades
- All Ceiling trim and above grid work needs to be completed in locker rooms by the end of this week
Hargrave
- Start Gym Partition Install
Carey
- Electrical Trim at any Area F painted locations and ceiling grid locations
- Speaker install at Gymnasium
Doherty
- Front Entry Ceiling
DCG
- Coping /Flashing install
Moran/Amber
- Trim at any ceiling grid locations
- Fabric Duct Install
Madden
Nelson
Consolidated
- Finish 1st floor VCT Install
- Start floor mitigation in North lobby
- Start Epoxy flooring in locker rooms
Week of 3/21/22 - 3/26/22
All Trades
- All Fire Caulking/Safing @ wall penetrations needs to be complete for Above Ceiling Inspection on 3/28
Carey Electric
- Transformer pad install
- Re-pipe @ Main entrance Doors for new Electric Strike Location
- Speaker installs @ Gymnasium
- IDF Rack install @ Area G
- All above ceiling ready for Inspection on 3/28
FE Moran/Amber
- Finish All communication wire @ Area F
- Finish All Through Wall Flashings
- Finish All Ceiling Diffusers in Area G/F
- All Above ceiling work completed
Eagle
Doherty
- Finish All Ceiling Grid
DCG
- Metal coping and flashing
Hargrave
- Gym equipment install
Madden
- Finish all Interior / Exterior caulking/ Door Hardware
Nelson
- Finish Sprinkler head install @ Area F Grid locations
Consolidated/PSI
- Moisture Mitigation @ North/West lobbies
Week of 3/28/22 - 4/2/22
All Trades
Hargrave
- Finish gym Equipment install
- Door install at Area G
Carey
- MDF Rack Install at Area G
- Gym equipment hook ups
Doherty
- RFP 014 soffit framing
- Drop Front entry ceiling
- Start ceiling tile install (Locker rooms/ Area g)
- Plan on exterior painting at Precast as soon as weather allows
DCG
- Coping/Flashing install
Moran/Amber
- Finish All Above ceiling work. All Flashings Sealed
Madden
Nelson
Consolidated
Week of 4/4/22 - 4/9/22
Carey Electric
- Re-pipe at Main entrance Doors for new Electric Strike Location
- AV rack install at Atea G
- Fire Alarm Inspection
- Gym equipment control install
- Pipe/ Wire to DOAS/RTU
FE Moran/Amber
- Finish trimming out at area G
- Finish Diffusers at Area F
Doherty
- Drywall/Tape at North/West Lobby vestibules
DCG
- Finish Metal coping and Flashing
Hargrave
- Finish Gym equipment install
- Start casework install at Area G
- Finish casework atArea F
- Finish Solid Surface Bench
- Start Scoreboard Install
Madden
- Finish Caulking/Door Hardware
Nelson
- Inspection set for Thursday
Consolidated/PSI
- Stock/ Start VCT in North/West lobbies/PE Offices
- Start Epoxy in Locker rooms
Jensens
- Water Meter Install
Week of 4/11/22 - 4/16/22
Hargrave
- FEC Install
- Door install at Area G
- Folding Partition Install at Science Rooms
- Finish Scoreboard Install
Carey
- Gym Equipment control install
Doherty
- RFP 014 soffit framing
- Fix any Degraded Areas on Air Barrier
- Drop Front entry ceiling
- Start ceiling tile install
- Plan on exterior painting at Precast as soon as weather allows
FE Moran
- RTU Install and All Associated Duct Work and Control Wiring
Jensens
- Begin Plumbing Trim
Nelson
Consolidated
- Finish Epoxy flooring in locker rooms
- Finish VCT @ North/West Lobbies
Week of 4/18/22 - 4/23/22
All Trades
Carey Electric
- AV rack install at Area G
- IDF Rack Install at area F
FE Moran/Amber
- RTU-2 Install and any Associated Ductwork/Control Wiring
- Finish all diffusers/grills
- Install Disconnects at RCP’s
Doherty
- Repair Air Barrier
- Install Plywood in IDF Rooms
- Wall Covering in North Lobby
- Access Panel Install
DCG
- Start Metal panel Install
Hargrave
- Finish casework install at Area G
- Finish Solid Surface Bench
- Finish Scoreboard Install
- Install Door Frames A 100-B, G 100-E
- Start Folding Partition at Science Rooms
- Bath Partition Install
- Projector Screen Install
Madden
- Finish Caulking/Door Hardware
Consolidated/PSI
- Finish VCT in PE offices, North lobby and IDF Room
- Start North Stairwell at Area G
- Floor protection at Locker Rooms
Jensens
- Start Plumbing Trim at Locker rooms
Nelson
- Install All Trims
Week of 4/25/22 - 4/30/22
All Trades
- All Ceiling and wall work to be completed in Gymnasium and Storage Room
- All Material and Equipment to be removed from the Gymnasium and Storage Room
Hargrave
- FEC Install
- Door/Hardware install at Area G
- Finish Folding Partition Install at Science Rooms
- Install Bath Accessories
Doherty
- Finish Ceiling Tile Install
- Plan on exterior painting at precast as soon as weather allows
FE Moran
- Finish RTU Install and All Associated Duct Work/Control Wiring
- Connect Fume Hood/Duct Work
Jensens
- Finish Plumbing Trim at Locker rooms
- Start Trim at Science Rooms
DCG
- Metal Panel Install
Consolidated
- Finish North Stairwell @ Area G
Mastership
- Apply Anti-Graffiti Spray
Week of 5/2/22 - 5/7/22
Carey Electric
- AV rack install at Area G
- Outlet install at are G casework (coordinate with Hargrave)
FE Moran/Amber
- RTU-2 Install and any Associated Duct work/Control Wiring
- Finish all diffusers/grills
- Install Disconnects at RCP’s
- Fume hood Vent Connection 5/5
Doherty
- Wall Covering in North Lobby
- Access Panel Install
- Paint touch- up in Gym and Area F storage
- Paint HM Doors
DCG
- Finish RFP 014 Existing Roof/ Area G Roof
Hargrave
- Finish casework install at Area G
- Install Door Frames A 100-B, G 100-E
- Finish Bathroom Accessories
- Swing HM Doors/Wood Doors
- Finish Fume Hood Install by 5/4
Jensens
- Trim in Area G
Mastership
- Apply Anti-Graffiti Spray
- Replace Damaged Face Brick @ 2 locations
Week of 5/9/22 - 5/14/22
Week of 5/16/22 - 5/21/22
Carey Electric
- All LV complete
- Outlet install at are G casework (coordinate with Hargrave)
- Light Pole Feeds at west End
FE Moran/Amber
- Finish all diffusers/grills
Doherty
- Wall Covering in North Lobby
- Finish Paint at exterior precast
DCG
- Finish RFP 014 Existing Roof/Area G Roof
- Metal soffit panels
Hargrave
- Finish Bathroom Accessories
- Finish HM/Wood door/Hardware Install
- Scoreboard Install
- Start Cleaning (5/19-5/20)
Mastership
- Apply Anti-Graffiti Spray
- Replace Damaged Face Brick at 2 locations
- Enlarge access Panel Openings
- Infill at extra FEC
- Move Equipment to Front of Site
Consolidated
- Seal Concrete at Storage Area
- Finish Vinyl base/ Carpet squares (coordinate with PSI)
- Carpet at vestibules
Week of 5/23/22 - 5/28/22
Week of 5/31/22 - 6/4/22
Hygieneering
- Begin Abatement
Phase 2 MEP’s
- Cut /Cap at Demo Areas 6/2
- Safe all Areas for Demo 6/2
- Begin 2nd Floor Demo 6/4
- Begin locker room/Bathroom demo 6/2
LoDestro
- Begin 2nd Floor Demo 6/4
- Begin locker room demo 6/2
- Floor protection install 5/31
Johler
- Begin/Finish Demo at Area C 6/1‐6/3
- Begin ceiling demo at Area E/D 6/4
- Begin Stairwell Demo 6/4
Phase 1 MEP’s
- Begin demo at Area C 6/1
Flo‐tech
- Classroom Unit ventilator demo
Hargrave
- Floor/Casework protection at Area C (coordinate with Johler)
Doherty
- Finish Paint touch‐ups
- Finish Exterior Paint
DCG
- Metal Soffit Panels at Area G
Carey
- Run Feeds for RTU‐1
FE Moran
- Start Up RTU‐1 6/3
Week 6/6/22 - 6/11/22
Hygieneering
- Continue Abatement
MEP’s
- Finish 2nd Floor Demo
- Begin 1st Floor Demo/Mechanical room
LoDestro
- Finish 2nd Floor Demo
- Begin 1st Floor Demo/Mechanical Room
- Begin concrete slab demo
M&I
- Steel Joist Reinforcement
Mastership
- Window Infill/Walls at Area C
Albrecht
- Excavation at Stairwell
Flo‐Tech
- Fluid Cooler/Pad Removal
DCG
- Metal Soffit Panels at Atea G
Week of 6/13/22 - 6/18/22
Westbrook Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 -7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 12/13/21 - 12/18/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 and 11/29/21
- Week of 12/6/21 - 12/11/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 & 2/7/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 & 2/21/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 & 3/15/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 & 4/4/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 -4/23/22
- Week of 4/25/22 & 5/2/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 & 5/16/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week of 6/6/22 - 6/11/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Riemer
- Construction entrances
- Temp access roads
- Jobsite trailer
- Excavate for footings
- Excavate for storm trap
- Grade south playground area
- Tree removal at north property line
American
- Temp power to trailer
Eagle
- Frame/Reinforce/Pour (F/R/P)
Johler
- Demo existing canopy (partial), overhangs, and interior Classroom 41
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 -7/17/21
Week of 7/19/21 - 7/24/21
Riemer
- Excavate for footings
- Cut and fill for building
- Install sidewalks and curbs at playground area
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and foundation walls
- Complete base slab for storm trap
- F/R/P stoop at door 41A
Mastership
- Tooth door opening 41A
Monarch Construction
- Complete footing demolition at south end B-wing
DeKalb Mechanical
- Reroute mechanical piping/reinstall CUV in classroom 41
American
- Power to construction trailer
Week of 7/26/21 - 7/31/21
Riemer
- Backfill footings
- Continue site grading
- Stone access for P/C erection
Siebert
- Landscape and surface install at playground
Action Fencing
- Install fence north property line
Spancrete
- Install deadmen for P/C installation
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and foundation walls
Madden Glass
- Install door 41A
Week of 8/2/21 - 8/7/21
Riemer
- Complete playground install
- Backfill foundations
Siebert
- Landscape and surface install at playground
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and walls
Spancrete
- Install P/C panels and planks
Monarch Construction
- Demo east canopy following removal of fluid coolers
Jensen's
- Start UG plumbing after install of P/C
DeKalb Mechanical
- Prepare existing piping for temporary chiller
American Electrical
- Prepare existing infrastructure for temporary chiller
Week of 8/9/21 - 8/14/21
Riemer
- Backfill foundations
- Backfill stormtrap
- Stone for parking on east side
Siebert
- Landscape install at playground
AJ Oleson
- Stormtrap installation
- Storm lines to/from stormtrap
Eagle
- Complete Frame/Reinforce/Pour (F/R/P) footings and walls
- Install shallow footings at MPC
- Prepare MPC roof deck for 6" topping placement
Mastership
- Tooth in around door opening 41A
Mobile Air
- Deliver temporary cooling tower
Monarch
- Install temporary door 41A
Jensen's
- UG plumbing
DeKalb Mechanical
- install valves/couplings for temporary cooling tower
- Demo air cooled chiller
American Electrical
- Install power requirements for temporary cooling tower
- Cut power to existing air cooled chiller
- Underslab rough-in at MPC area
Week of 8/16/21 - 8/21/21
Riemer
- Excavate for footings at A, 9, E and at canopy
- Backfill stormtrap
AJ Oleson
- Backfill perimeter of stormtrap
- Storm lines to/from stormtrap
Eagle
- F/R/P footings and walls
- Install shallow footings at MPC
- Place 6" topping placement at MPC roof
Mobile Air
- Temporary cooling tower start-up
Monarch
- Demo canopy
Jensen's
- UG plumbing
DeKalb Mechanical
- Demo existing fluid coolers
American Electrical
- Cut power to existing fluid coolers
- Underslab rough-in
Week of 12/13/21 - 12/18/21
Mastership
- Brick installation on Areas A & B walls
Monarch
- Install HM frames
Elens & Maichin
- Roofing
RB Construction
- Interior partition/soffit/ceiling installations
- Interior drywall installation
- Install Tectum Ceiling Panels in MPR
Madden Glass
- Windows in Area B (Week of 12/20/2021)
Nelson Fire Protection
- Above grade rough-in
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
- Set RTU1, MAU, PCU & DOAS
American Electrical
- Above grade rough-in
Week of 8/23/21 - 8/28/21
Riemer
- Final grade site
- Backfill foundations as required
- Stone building pad as required
AJ Oleson
- Storm lines to/from stormtrap, sanitary line, water lines
Eagle
- Place 6" topping slab on precast roof deck
- Complete F/R/P footings and walls
Spancrete
- Pull braces and deadman that interfere with other work
Mastership
- Start CMU load bearing walls
Monarch
- Complete canopy demo
Jensen's
- UG plumbing
American Electrical
- Underslab rough-in
Week of 8/30/21 - 9/4/21
Riemer
- Final grade site
- Backfill foundation as required
Oleson
- Storm lines to/from stormtrap, sanitary line, water lines
Mastership
- CMU load bearing walls along existing building
M&I Steel
- Begin structural steel installation
Elens & Maichin
- Temp patch existing roof
Jensen's
- UG plumbing
American Electrical
- Underslab rough-in
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Week of 9/20/21 - 9/25/21
Riemer
- Final grade for SOB P to X/1 to 7 (Friday 9/24)
Eagle
- Prep SOG to X/1 to 7 (Friday 9/24)
M&I Steel
- Structural steel installation north of P line (Monday thru Friday)
- Install metal roof decking south of P line (Monday thru Wednesday)
- Complete mezzanine steel/decking
Mastership
- Complete CMU walls in MPR (Monday thru Friday)
Elans & Maichin
- Check moisture requirements at MPR roof
- Mobilization for roofing P to X/1 to 7
RB Construction
- Layout for exterior wall installation (Thursday thru Friday)
- Begin installation of exterior walls (Thursday thru Friday)
Jensen's
- Prep P to X/1 to 7 for SOG placement (Wednesday, Thursday)
- Underground rough-in small addition end of B Wing (Monday - Wednesday)
DeKalb Mechanical
- On-site to coordinate opening in CMU walls at MPR with Mastership
American Electrical
- Underground rough-in P to X/1 to 7 (Wednesday, Thursday)
Week of 9/27/21 - 10/2/21
Riemer
- Finish grade SOG Area B (M)
- Backfill MPR bathrooms and finish grade MPR SOG
Eagle
- Prep/pour SOG Area B (T/W/Th)
- Prep/pour mezz deck
Oleson
- 24" (RFP-007WB) & RFP-014WB
M&I Steel
- Steel Delivery (M)
- Structural Steel North/East of MPR
Elans & Maichin
- Roof prep/install - Area B
- Test concrete topping on MPR
Jensen's
- UG plumbing at roof vents
American Electrical
- Underslab rough-in
RB Construction
- Exterior CFMF framing
- Interior wall layout
Week of 10/4/21 - 10/9/21
Riemer
- Final grade site & SOG
Oleson
- 24" (RFP-007WB) & RFP-014WB
Eagle
- Prep/pour SOG Area B & MPR
M&I Steel
- Structural Steel North/East of MPR
Jensen's
- In wall rough and roof vents
American Electrical
- In wall rough and roof vents
DeKalb
- Ductwork and in wall rough
RB Construction
- Exterior CFMF framing
- Interior wall layout
Elens & Maichin
- Roof prep/install Area B/MPR
Week of 10/11/21 - 10/16/21
Riemer
- Finish grade site & SOG
Eagle
- Prep/pour SOG MPR (Monday 10/11 to Tuesday 10/12)
Mastership
- CMU walls for rooms A121. A122, A123, A124 (Thursday 10/14 to Friday 10/15)
M&I Steel
- Complete structural steel/decking installation
Elens & Maichin
- Roofing
RB Construction
- Exterior wall Installation
- Install air/vapor barrier B-wing walls
- Install perimeter rigid insulation B-wing walls
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above and below grade (kitchen) rough-in
DeKalb Mechanical
- Above grade rough-in
American Electric
- Above and below grade rough-in
Week of 10/18/21 - 10/23/21
Riemer
- Final grade for SOG E to N/9 to 11, K to P/4 to 9, D to P/1 to 4 (Tuesday)
- Final grade site
Eagle
- Prep/pour SOG E to N/9 to 11, K to P/4 to 9, D to P/1 to 4 (Wednesday, Thursday)
Mastership
- Begin brick installation on Area B walls
Elens & Maichin
- Roofing - Area B wing and MPR
RB Construction
- Exterior wall installation (Area A, roofing transitions, Area B)
- Install air/vapor barrier Area B walls
- Install perimeter rigid insulation Area B walls
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in in Area B
- Underground work in kitchen
DeKalb Mechanical
- Above grade rough-in
- Set DOAS curb
American Electrical
- Above and below grade rough-in
Week of 10/25/21 - 10/30/21
Riemer
- Final grade site
- Proof roll/stone all drives/ parking pads
Eagle
- Place SOG D to P/1 to 4
Mastership
- Brick installation on Area B walls
M&I Steel
- Install stair to mechanical mezzanine
Monarch
- Install door frames Area B
- Board up exterior openings
Elens & Maichin
- Roofing - complete MPR, east and south sides MPR
RB Construction
- Exterior wall installation
- Interior partition installation
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in
- Kitchen underground
DeKalb Mechanical
- Above grade rough-in
American Electric
- Above grade rough-in
Week of 11/1/21 - 11/6/21
Eagle
- Prep/pour SOG A to D/1 to 4, kitchen area (freezer/cooler base)
Mastership
- Brick installation on Area B walls
Monarch
- Install door frames Area B
- Board up exterior openings
Elens & Maichin
- Roofing
RB Construction
- Exterior wall installation
- Interior partition installation
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in
- Complete kitchen underground
DeKalb Mechanical
- Above grade rough-in
- Complete install of temp heating system
American Electric
- Above grade rough-in
Week of 11/8/21 - 11/13/21
Reimer
- Complete grading of east side and stone all drives and parking areas
AJ Oleson
- Watermain and sanitary sewer on north side
- Complete storm sewers on south side
Eagle
- Prep/Pour SOG A to D/1 to 4, Kitchen area
Elens & Maichin
- Roofing Areas W & T
Mastership
- Brick installation on Area B walls
Monarch
- Install door frames area B
- Board up exterior openings
Elens & Maichin
- Roofing
RB Construction
- Exterior Wall Installation
- Interior partition installation
Jensen’s
- Above grade rough-in
- Install grease trap
DeKalb Mechanical
- Above grade rough-in
- Complete install of temp heating system
American Electrical
- Above grade rough-in
Week of 11/15/21 - 11/20/21
Riemer
- Silt fence at stockpile
Oleson
- Set sanitary manhole C and coord. with plumber for grease trap piping
M&I Steel
- Deliver L2 lintels on Thursday
Mastership
- Brick installation Area B walls
Monarch
- Install HM frames
- Complete board-up
Elans & Maichin
- Roofing Areas X, Y (Areas available now for final roofing – V, W, Z and AA)
- Plywood backside of parapet walls currently open to below - CRITICAL
RB Construction
- Exterior Wall Installation
- Exterior soffit framing
- Interior partition installation
- Complete AVB
- Spray foam
Jensen’s
- Above grade rough-in
- Set grease trap
- Set vents at roof Areas R and S (Coordinate with Elens & Maichin)
DeKalb Mechanical
- Above grade rough-in
- Set DOAS curb at roof Area T??? (Coordinate with Elens & Maichin)
- Set exhaust curb at roof Areas R and S (Coordinate with Elens & Maichin)
American Electrical
- Above grade rough-in
- Directional bore for ComEd primaries
Week of 11/22/21 and 11/29/21
Mastership
- Brick installation on Areas A & B walls
Monarch
- Install HM frames
Elans & Maichin
- Roofing
RB Construction
- Interior partition installation
Madden Glass
- Windows in Area B (Week of 11/29/2021)???
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
American Electrical
- Above grade rough-in
Week of 12/6/21 - 12/11/21
Eagle
- Pour 3 missing pier supports
Mastership
- Brick installation Area B walls
Monarch
- Install HM frames (A101, A102, A103, A104, A105, A106, A107, A108)
- Install balance of HM borrowed lite frames in corridor 010
Elens & Maichin
- Roofing Areas T, W, Z, AA
RB Construction
- Complete exterior soffit framing with plywood sheathing
- Complete spray foam exterior overhang eaves
- Patch spray foam in exterior walls where exterior pilasters poke through
- Interior partition installation
- Start drywalling corridor 010
- Start framing soffits in corridor 10
- Start framing in kitchen (after ductwork, coordinate with plumber)
Nelson Fire Protection
- Install piping Area A (Except MPR)
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
American Electrical
- Above grade rough-in
- Directional bore for ComEd primaries
Week of 1/10/22 - 1/15/22
Elens & Maichin
- Roofing roof area Q
- Patch between existing and new roof
- Eaves/Fascia/Soffit
Madden Glass
- Window installation
Mastership
- Brick and window sill installation Area A
- Clean brick Area A
- Interior CMU at MPR
- AVB exterior CMU where abuts existing building
- Interior brickwork
M&I Steel
- Set chiller framing (Thursday/Friday)
RB Construction
- Interior drywall hanging and taping
- Misc framing for soffits/ceilings
- Layout corridor 10 ceiling
Nelson Fire Protection
- Hang sprinkler piping in MPR
- Misc rough-in as required
- Adjust piping in soffits of A111 Reading room, A125, Verify Corridor 09
Jensen’s
- Misc rough-in as required
DeKalb Mechanical
- Misc rough-in as required
American Electrical
- Misc rough-in as required
Week of 1/17/22 - 1/22/22
AJ Oleson
- Sanitary Sewer
- Water Line
Madden Glass
- Window installation
Mastership
- Misc masonry where required
RB Construction
- Interior drywall hanging and taping
- Misc framing for soffits/ceilings
- Begin painting TBD
Nelson Fire Protection
- Misc rough-in as required
Jensen’s
- Misc rough-in as required
DeKalb Mechanical
- Misc rough-in as required
American Electrical
- Misc rough-in as required
Week of 1/24/22 - 1/29/22
AJ Oleson
- Sanitary Sewer
- Water Line
Eagle
- Grind/Patch floor in Kitchen and MPR
Spancrete
- Clean saw cut paste from face of wall in MPR
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- Clean brick Area A (weather permitting)
- Complete exterior brick (weather permitting)
- Interior CMU at MPR
- Interior brickwork
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
RB Construction
- Misc Framing
- Columns and window seats at Area B Classrooms
- Interior drywall hanging and taping
- Hang/tape drywall in main electrical room
- Corridor 10
- Outside walls Area B
- Rooms A132 and A133
- Ceilings in toilet rooms Area B
Jensen’s
- Misc rough-in as required
- Install valve tags
- Fire safe/Seal wall penetrations
DeKalb Mechanical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 1/31/22 & 2/7/22
Madden Glass
- Window installation
Consolidated
- Toilet room finish install (Week of 1/31/22)
RB Construction
- Misc framing
- Interior drywall hanging and taping
- Painting
- Mechanical Mezz (Week of 1/31/22)
- MPR Ceiling (Week of 1/31/22)
- A109 Area
- Area B Classrooms (Week of 2/7/22)
Jensen’s
- Misc rough-in as required
- Valve extensions and tags
- Fire safe/Seal wall penetrations
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- Install AHU-1 (week of 02/07/2022)
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 2/7/22 - 2/12/22
Spancrete
- Clean saw cut paste from face of walls in MPR
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- Clean exterior brick Area A (weather permitting)
- Complete exterior brick (weather permitting)
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
Consolidated
- Toilet room finish install
RB Construction
- Misc framing
- Interior drywall hanging and taping
- Painting
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- MPR louver/damper installations
- Install AHU-1
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 2/14/22 & 2/21/22
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Window installation
Consolidated
- Toilet room finish install
RB Construction
- Misc framing
- Interior drywall hanging and tapingo Painting
- Install ceiling grid classrooms (week of 02/21/2022)
Nelson Fire Protection
- Trim to grid (Week of 02/21/2022)
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- MPR louver/damper installations
- Trim to grid (Week of 02/21/2022)
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
- Trim to grid (Week of 02/21/2022)
Week of 2/28/22 - 3/5/22
AJ Oleson
- Sanitary and water installation (Weather permitting)
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
RB Construction
- Interior drywall hanging and taping
- Painting
- Install ceiling grid classrooms
Nelson Fire Protection
- Trim to grid
DeKalb Mechanical
- Install AHU #1
- Trim to grid
American Electrical
- Electrical Rooms
- Misc rough-in as required
- Trim to grid
Week of 3/7/22 & 3/15/22
Eagle
- Complete stoops
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
Monarch
- Install Hood and stainless wall panels on north wall kitchen (Week of 3/7)
Consolidated
- Epoxy flooring in toilet rooms
RB Construction
- Interior drywall hanging and taping
- Painting
- Install ceiling grid classrooms
- Install tectum wall panels in MPR (Week of 3/7)
Nelson Fire Protection
- Trim to grid
Jensen’s
- Fixture install in toilet rooms (Week of 3/15 pending completion of epoxy flooring)
DeKalb Mechanical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
- Trim to grid
American Electrical
- Electrical Rooms
- Misc rough-in as required
- Trim to grid
Week of 3/21/22 - 3/26/22
AJ Oleson
- Storm, Sanitary and Watermain installation
Eagle
- Complete stoops
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Exterior Door installation
Consolidated
- Mitigation (Starting 03/23/2022)
- Epoxy flooring in toilet rooms (Starting 03/25/2022)
RB Construction
- Soffit/Walls/Ceiling between new and existing buildings
- Complete ceiling grid all areas
- Taping Pre-K Classrooms
- Painting
Nelson Fire Protection
- Trim to grid
Jensen’s
- Video underground for Ph 2 work
DeKalb Mechanical
- Ductwork in mechanical mezzanine
- Complete HVAC in Pre-K
- Install radiant ceiling panels
- Remove ceiling CUH and two CUH in link between old/new buildings
American Electrical
- Electrical Rooms
- Trim to grid
- Conduit through to boiler room
- Install ComEd primary conduit
Week of 3/28/22 & 4/4/22
AJ Oleson
- Complete underground as necessary
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring in toilet rooms
- Complete floor mitigation
- VCT (Week of 03/28/2022)
- Carpeting (Start 03/29/2022)
RB Construction
- Painting
- Hang balance of drywall in Pre-K
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
Upcoming work: Toilet Fixtures (Week of 04/04/2022)
Casework (Week of 04/11/2022)
Week of 4/4/22 - 4/9/22
AJ Oleson
- Complete underground
Eagle
- Grind floors in MPR toilet rooms
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Complete floor mitigation
- Carpeting in classrooms
RB Construction
- Painting
- Complete framing soffit/walls/ceiling between new and existing buildings
- Hang balance of drywall in Pre-K
- Taping Pre-K Classrooms
Jensen’s Plumbing
- Install toilet room fixtures
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
- Trim to grid
- Begin trim-out of voice/data cabling
Week of 4/11/22 - 4/16/22
AJ Oleson
- Complete underground as necessary
Riemer
- Site Grading
- Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring in Kitchen (partial), MPR toilet rooms and janitor’s closets
- VCT
- Carpeting
RB Construction
- Painting
- Hang balance of drywall in Pre-K
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
- Install ComEd secondary conduit
- Install site electric east
Week of 4/18/22 -4/23/22
Riemer
- Site Grading
AJ Oleson
- Complete storm underground
Eagle
- Grind floors in MPR toilet rooms
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Carpeting in classrooms
- VCT in corridors
Monarch
- Casework
RB Construction
- Complete framing soffit/walls/ceiling between new and existing buildings
- Complete framing vestibule A6
- FRP in kitchen
- Hang balance of drywall in Pre‐K
- Taping Pre‐K Classrooms
Jensen’s Plumbing
- Install toilet room fixtures
- Above ceiling punch items
DeKalb Mechanical
- Trim in kitchen
- Hang duct in MPR
- Above ceiling punch items
American Electrical
- Site electrical
- Fire Alarm Trim
- Receptacle trim
- Complete audio/visual in MPR
- Above ceiling punch items
Week of 4/25/22 & 5/2/22
Riemer
- Site Grading
- Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring MPR toilet rooms and janitor’s closet
- VCT
- Carpeting
- Ceramic tile in Area A and Pre‐K toilet rooms
Monarch
- Casework
- Toilet accessories and partitions
- Gym equipment
- Coiling doors in MPR
RB Construction
- Complete taping in Pre‐K
- Painting
- Ceiling tile install
- Complete ceiling grid in Area A
- Ceiling grid in Pre‐K
Nelson
- Trim to grid in Pre‐K
Jensen’s
- Install fixtures in casework
DeKalb Mechanical
- Trim to grid in Pre‐K
American Electrical
- Electrical Rooms
- Trim to grid in Pre‐K
- Site electric
Week of 5/2/22 - 5/7/22
Riemer
- Site Grading & Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Carpeting in classrooms
- VCT in corridors
- Ceramic tile Pre-K
Monarch
- Install wood and HM doors
RB Construction
- Complete drywall vestibule A6
- Painting in Pre-K
- Install ceiling grid Pre-K
- Install ceiling tile
DeKalb Mechanical
- Insulate ductwork Pre-K
American Electrical
- Site electrical
- Fire Alarm Trim
- Receptacle trim
- Low voltage trim
Week of 5/9/22 & 5/16/22
Riemer
- Site Grading & Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring MPR toilet rooms and janitor’s closet
- VCT
- Carpeting
- Ceramic tile in Area A and Pre-K toilet rooms
Monarch
- Wood and HM doors
- Toilet accessories and partitions
- Gym equipment
- Coiling doors in MPR
RB Construction
- Painting (Interior and exterior)
- Ceiling tile install
- Complete ceiling grid
Nelson
- Trim to grid in Pre-K
Jensen’s
- Install fixtures in casework
DeKalb Mechanical
- Trim to grid in Pre-K
American Electrical
- Electrical Rooms
- Fire Alarm
- Low Voltage
- Trim to grid in Pre-K
- Site electric
Week of 5/16/22 - 5/21/22
Riemer
- Cut for curbs and drives
AJ Oleson
- Adjust frames on MH/CB’s
Eagle
- Sidewalks and curbs
Elens & Maichin
- Roof Screens
Monarch
- Install doors and hardware
- Install coiling doors
- Install basketball equipment
- Install toilet accessories
Madden Glass
- SF entrance installation
Consolidated
- Complete VCT
- Epoxy flooring in Kitchen (partial), MPR toilet rooms and janitors’ closets
RB Construction
- Paint exterior Precast
- Complete drywall ceilings
- Install ceiling tiles
- Ceramic tile install
Nelson
- Trim to grid in Pre‐K
DeKalb Mechanical
- Trim to grid in Pre‐K
American Electrical
- Trim to grid in Pre‐K
- Misc. lighting and trim out
Week of 5/23/22 - 5/28/22
Phase 1
Riemer
- Cut for drives
Eagle
- Walks and curbs
K&L
- Prep for asphalt paving
M&I
- Angles and plates at coiling door walls in MPR
Mastership
- CMU walls in MPR
Elens & Maichin
- Complete roof screens
Monarch
- Install doors and hardware Pre‐K
- Install casework in Pre‐K
Madden Glass
- Caulk and complete glazing
Consolidated
- Mitigate Pre‐K corridor
- VCT
- Carpeting
- Complete ceramic tile
RB Construction
- Painting
- Ceilings in Pre‐K
Jensen’s Plumbing
- Trim in Pre‐K
DeKalb Mechanical
- Begin demo in boiler room
American Electrical
- Misc trim
Phase 2
Monarch
- Install floor protection
- Begin demolition existing toilet room
Jensen’s Plumbing
- Demo existing toilet room
American
- Demo existing toilet room
Week of 5/31/22 - 6/4/22
Phase 1
Riemer
- Backfill curbs
- Cut roadway where required
- Proof roll
- Excavate for storm trap and door F footings
Eagle
- Walks
K&L
- Prep for asphalt paving
Mastership
- CMU walls in MPR
Elens & Maichin
- Install roof screens
Monarch
- Complete install of coiling doors
- Install interior partition at Door F
- Demo for Door F construction
Consolidated
- Mitigate Pre-K corridor and seal mezzanine concrete
- VCT
- Carpeting
- Complete ceramic tile
RB Construction
- Painting
- Complete drywall install and tape
Jensen’s Plumbing
- Misc trim
DeKalb Mechanical
- Begin demo in boiler room
American Electrical
- Misc trim
- Site work
Phase 2
Others
- Abatement
- Move classroom furniture
Monarch
- Install floor protection
- Begin demolition existing toilet room
- Begin demolition classroom wing
Jensen’s Plumbing
- Demo existing toilet room
- Layout for floor removal
Helm
- Demo
American
- Demo existing toilet room
Week of 6/6/22 - 6/11/22
Phase 1
Riemer
o Backfill curbs/respread
o Complete excavation of storm trap
Eagle
- Walks and concrete paving
- Footings at door F
- Storm trap base slab
Mastership
- CMU walls in MPR
Monarch
- Remove ceiling in corridors 03 and 04
- Final clean classrooms
- Casework Pre-K classrooms
Consolidated
- VCT MPR and Pre-K
- Carpeting
RB Construction
- Painting
Jensen’s Plumbing
- Boiler Room
DeKalb Mechanical
- Demo boiler room
American Electrical
- Misc
- Site Work
Phase 2
Monarch
- Classroom demolition
- Board-up Openings
Mastership
- Cut door openings/Infill Unit Vents
Commercial
- Demo flooring in existing building
Jensen’s Plumbing
- Demo existing toilet room
Helm
- Demo existing toilet room
- Demo classrooms
American
- Demo existing toilet room
Ground Breaking
On May 17, 2021, the D34 Board of Education, Village Representatives, administrators and students broke ground at Lyon, Westbrook and Henking elementary schools and Springman Middle School.
An Overview
On March 17, 2020, the community approved a referendum for $119 million to allow District 34 to repair, replace and update our buildings. The impact of the referendum will positively impact the community for decades to come, and it will be felt at every school, in every classroom, by every District 34 student. We recognize that we are tasked with Building Future.
Financial Update
On Monday, March 29, the Board of Education approved just under $53M in bids for the Phase 1 construction of the capital improvements approved by voters in last year's referendum. That amount is $4.5M less than expected.
D34 Special Board of Education Meeting: Construction Bid Approval
On December 15, 2020, District 34 received 11 bids and secured a deal with R.W. Baird & Co. with a cost of 0.943% (including interest rates, underwriter's discount and all costs of issuance). This rate is much lower than the 1.96% estimate presented to the Board of Education on October 27, 2020 and represents a significant savings and benefits for taxpayers:
- The extremely competitive bid reduced the final maturity of the Series 2021 bonds by one year and also reduced the final maturity of the total $119M referendum plan by one year.
- The shorter overall amortization resulted in total debt service with $10M less interest cost over the life of the bonds than shown at the October 27, 2020 presentation to the Board of Education.
The low rate received is due to District 34's Aaa rating from Moody’s Financial Services, the highest possible rating.
Construction Updates
At the November 16 Board of Education Meeting, Dave Torres from construction manager Nicholas & Associates gave an update of the design stages, a budget update and an overview of the timeline and scope of construction. The District will go out to bid in February 2021, with Board approval in March and construction starting in April 2021 on the additions at Henking, Lyon, Westbrook and Springman.
Henking
The construction will add space for full-day kindergarten, include a multi-purpose room addition and update classrooms (acoustic, flooring, other).
In addition to the extra space, construction will improve the following areas of Henking School:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- New kindergarten addition, including multipurpose room
- Classroom environment
Henking Rendering Photo Gallery
Lyon
The construction will add space for full-day kindergarten, include a multipurpose room addition, create a courtyard playground and update classrooms; as well as the following:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Electrical wiring, panel and service replacement
- Additional main office space
- Classroom environment (acoustic, flooring, other)
Lyon Rendering Photo Gallery
Westbrook
The construction will include a multi-purpose room addition and a two-classroom addition and existing classroom renovations for the District 34 early childhood program (pre-kindergarten) full-day kindergarten.
In addition to the construction at Westbrook School there will be improvements in:
- Traffic flow
- ADA improvements
- Fire suppression sprinkler system throughout
- Site reconfiguration to address traffic flow and provide underground stormwater detention
- Storm shelter
- Classroom environment (acoustics, flooring, other)
Westbrook Rendering Photo Gallery
Springman
The following areas will be focused on to improve Springman:
- Upgrading science labs to meet national standards*
- Creating additional special education spaces
- Consolidating and relocating offices to increase security and provide students with better access to staff
- Reconfiguring stairways to improve safety and meet current codes
- Relocating the cafeteria to improve the student experience, supervision, acoustics, and ADA accessibility
- Moving locker rooms out of the basement to improve supervision and accessibility
*Attea labs will also be updated so all D34 middle school students learn in labs that support Next Generation Science Standards.
Construction will also focus on the following:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Site reconfiguration including underground stormwater detention
- New entry addition at main office
- Renovation of east gym to become new cafeteria
- Mechanical, electrical and plumbing replacement
- New south gym addition
- Classroom environment (acoustics, flooring, other)
Springman Rendering Photo Gallery
Construction expenditures for 2021 are expected to be just under $53M. Citizens Finance Advisory Committee (CFAC) on the debt structure for the referendum.
CFAC recommendations include:
- Issue more debt sooner to take advantage of lower interest rates
- Accelerate the debt payment schedule to save taxpayer dollars
- Delay the use of fund balance
Taking these steps will reduce the tax burden on the community.
Elizabeth Hennessy, Managing Director, Raymond James & Associates, gave a referendum financing update based on the CFAC recommendation. The recommendation of an accelerated option could mean that taxpayers would pay approximately $22M less than the original amount outlined in the referendum.
Rendering Photo Gallery
Summary of Planned School Improvements
Attea
Attea Middle School is one of the youngest schools in District 34. Built in 2003, Attea serves nearly 900 students in grade 6-8. Similar to Springman Middle School, Attea science labs will also be updated to meet the national standards, therefore all D34 middle school students learn in labs that support the Next Generation Science Standards.
In addition to the update in science classrooms, Attea will also have the following improvements completed:
- Complete roof replacement
- Interior and exterior maintenance
- Fire alarm system replacement
- Intercom system replacement
- Lighting replacement
- Classroom environment (acoustics, flooring, other)
Attea Rendering Photo
Glen Grove
Built in 1959, Glen Grove School serves more than 500 students in grade 3-5.
The following improvements will be completed at Glen Grove:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Electrical service replacement
- Lighting replacement throughout
- Classroom improvements (acoustics, flooring, other)
Henking
Hoffman
Hoffman School was built in 1959 and serves more than 530 students in grade 3-5.
The construction will add the following improvements to Hoffman:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Select electrical panel replacement
- Additional main office space
- Additional multipurpose room space
- Classroom environment (acoustics, flooring, other)
Lyon
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Electrical wiring, panel and service replacement
- Additional main office space
- New kindergarten addition, including multipurpose room
- Classroom environment
Pleasant Ridge
Built in 1960, Pleasant Ridge School serves nearly 550 students in grades 3-5. With construction happening throughout the District, Pleasant Ridge will have the following improvements:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Classroom environment (acoustics, flooring, other)
Springman
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Site reconfiguration including underground stormwater detention
- New science lab addition
- Added space for special education programs
- New entry addition at main office
- Renovation of east gym to become new cafeteria
- Mechanical, electrical and plumbing replacement
- New south gym addition
- Relocation of interior exit stairs and elevator
- Classroom environment
Westbrook
- ADA improvements
- Fire suppression sprinkler system throughout
- Site reconfiguration to address traffic flow and provide underground stormwater detention
- New kindergarten addition
- Storm shelter
- Two-classroom addition and interior renovation for District 34 early childhood program (pre-kindergarten)
- Classroom environment
Summer 2020 Pre-Construction Community Meetings
D34 provided the community an opportunity to hear from architects, engineers and construction management about site plans, grading and drainage, materials, elevations, and other zoning issues that relate to construction at Henking Elementary School, Lyon Elementary School, Westbrook Elementary School and Springman Middle School. You can view recordings of the virtual meetings, and presentations that include renderings of the schools.
June 25, 2020 Community Meeting: Henking, Lyon, Westbrook Construction Updates
- Meeting recording (Password: PrimaryUpdate34!)
- Presentation slides
August 11, 2020 Community Meeting: Springman Construction Update
- Meeting recording (Password: SpringmanUpdate34!)
- Presentation slides
Summer Construction Updates
2020
- Weekly Construction Update: June 29, 2020
- Weekly Construction Update: July 6, 2020
- Weekly Construction Update: July 20, 2020
- Weekly Construction Update: July 29, 2020
- Weekly Construction Update: August 29, 2020
Weekly Construction Update: June 29, 2020
Work is currently ongoing at both Hoffman Elementary School and Springman Middle School. Below is a recap of recent activities and some pictures associated with the current progress.
-
Hoffman Roof Area E roof installation is complete
-
Walls for Area E are framed now just need metal wall panels installed (few weeks out)
-
Hoffman Area (P, Q and D) are all cap sheeted and waiting on coating
-
Brick work at Springman ongoing for new roof flashing
-
Tear of on Area R1 at Springman 6/24
-
Will be starting demo on Area C Thursday or Friday this week
-
R1 will be complete in 2 more full days of work
-
Sheet Metal will start on coping at Hoffman this week
-
We are currently on schedule and under budget
-
Substantial Completion is August 7
Weekly Construction Update: July 6, 2020
Work continues at Hoffman Elementary School and Springman Middle School. Below is a recap of recent activities and some pictures associated with the current progress.
-
(Hoffman) Roofing work is 90% complete
-
(Hoffman) Face brick removal for new flashing is underway
-
(Springman) Brick work for new through wall flashing is complete
-
(Springman) Roof Area R1 is 95% complete
-
(Springman) Continue roof work at area C
-
Sheet metal work continues at both Schools
-
We are currently on schedule and under budget. Substantial Completion is August 7th
Weekly Construction Update: July 20, 2020
Work continues at Hoffman Elementary School and Springman Middle School. Below is a recap of recent activities and some pictures associated with the current progress.
-
(Hoffman) Roofing is 100% complete & Sheet Metal is 70% complete
-
(Hoffman) New face brick and mechanical reconnection work is underway
-
(Springman) Roof Area R1 is 95% complete
-
(Springman) Roof Area C will be ready for final coating midweek
-
Roof drain insulation work is ongoing at both buildings
We are currently on schedule and under budget. Substantial Completion is August 7th
Weekly Construction Update: July 29, 2020
Work continues at Hoffman Elementary School and Springman Middle School. Below is a recap of recent activities and some pictures associated with the current progress.
-
(Hoffman) Roofing is 100% complete and Sheet Metal is 70% complete
-
(Hoffman) Mechanical and Electrical reconnections are 95% complete
-
(Springman) Roof Area R1 is 95% complete
-
(Springman) Roof Area is C is 90% complete
-
(Springman) Roof Hatch is 75% complete
-
Roof drain installation is complete at both locations
-
We are currently on schedule and under budget. Substantial Completion is August 7
Weekly Construction Update: August 29, 2020
2019
- Information
- Weekly Construction Update: June 12, 2019
- Weekly Construction Update: June 19, 2019
- Weekly Construction Update: June 26, 2019
- Weekly Construction Update: July 3, 2019
- Weekly Construction Update: July 10, 2019
- Weekly Construction Update: July 17, 2019
- Weekly Construction Update, July 24, 2019
- Weekly Construction Update: July 31, 2019
- Photos
Information
At the November 2018 meeting, the District 34 Board of Education approved $9.8M in bonds to address critical facility needs. The work taking place in the summer of 2019 includes:
- Electrical panels and other electrical work
- Boilers
- Generators
- Ventilators
- Sump pumps
- Radiator covers
- Air handling units
- Roofing (particularly to address significant leaking)
- Concrete sidewalk replacement
- Other critical maintenance issues
These projects will be finished in time for buildings to be ready to welcome back staff and students in August.
Weekly Construction Update: June 12, 2019
Construction commencement was this past Wednesday 6/12. Throughout the course of last week and this week selective interior and exterior demolition is taking place at every building. This work specifically includes:
- Ceiling removal for new mechanical & electrical work at the District Office, Westbrook, Springman, Pleasant Ridge & Glen Grove.
- Interior Mechanical, Electrical & Plumbing disconnect and demolition work at all locations.
- Masonry wall demolition to enlarge/create openings for new Mechanical equipment at Glen Grove, Henking & Pleasant Ridge.
- Exterior site demolition which includes pavement removal and prep work at Attea, Pleasant Ridge & Westbrook.
- Vacuuming roofs at Westbrook, Henking, Springman, Glen Grove & Pleasant Ridge.
Some of the NEW construction is also underway this week including:
- Exterior site work (concrete walks and asphalt patching) at Pleasant Ridge, Westbrook & Attea
- Above ceiling and roof top Mechanical, electrical & Plumbing work at all locations.
- New roof work at Springman, Henking, Glen Grove, Pleasant Ridge
Weekly Construction Update: June 19, 2019
We are off to races!!! Construction commencement was this past Wednesday 6/12. Throughout the course of last week and this week selective interior and exterior demolition is taking place at every building. This work specifically includes:
- Ceiling removal for new mechanical & electrical work at the District Office, Westbrook, Springman, Pleasant Ridge & Glen Grove.
- Interior Mechanical, Electrical & Plumbing disconnect and demolition work at all locations.
- Masonry wall demolition to enlarge/create openings for new Mechanical equipment at Glen Grove, Henking & Pleasant Ridge.
- Exterior site demolition which includes pavement removal and prep work at Attea, Pleasant Ridge & Westbrook.
- Vacuuming roofs at Westbrook, Henking, Springman, Glen Grove & Pleasant Ridge.
Some of the NEW construction is also underway this week including:
- Exterior site work (concrete walks and asphalt patching) at Pleasant Ridge, Westbrook & Attea
- Above ceiling and roof top Mechanical, electrical & Plumbing work at all locations.
- New roof work at Springman, Henking, Glen Grove, Pleasant Ridge
Weekly Construction Update: June 26, 2019
This week, we are wrapping up interior and exterior demolition work across the multiple sites. Roof work is well underway at Henking and Springman with Glen Grove and Westbrook gearing up to start this week. At Attea, we are prepping for the new generator installation which includes underground gas & electrical piping and associated concrete work. The first of our mechanical units to arrive will be installed this week at Pleasant ridge! The following work is also scheduled for this week:
- Masons are onsite infilling louver openings at Springman and installing thru-wall flashing at Westbrook.
- Fire Alarm work has started at the district office.
- Above ceiling mechanical, electrical & plumbing work is on going at most of the buildings.
Weekly Construction Update: July 3, 2019
At the half-way point, this week all interior and exterior demolition will be complete. Work scheduled for this week specifically includes:
- Mechanical equipment curbs are being set at multiple locations alongside the roof work.
- New Mechanical equipment is scheduled for delivery with installation right around the corner.
- Roof drain replacements & modifications are taking place alongside the roofers.
- Roof work at Springman and Henking is scheduled for completion.
- Roofing work continues at Westbrook, Glen Grove and Pleasant Ridge
- Drywall and Taping at Springman for mechanical equipment enclosures
- Concrete placement at Attea for the new generator.
- Above ceiling electrical & plumbing work at all locations is ongoing
Weekly Construction Update: July 10, 2019
This week’s work includes:
- Ongoing Roof work at Westbrook, Lyon (to be completed this week), Pleasant Ridge & Glen Grove
- Mechanical units are being set at Henking, Glen Grove & Westbrook.
- Roof drain replacements are ongoing in conjunction with the roof work.
- Unit ventilator enclosures are being taped and prepped for paint at Springman
- New concrete site work at pleasant ridge
- Above Ceiling final inspection for mechanical, electrical & plumbing work is scheduled for Friday at Henking, Springman, Glen Grove & Westbrook.
Weekly Construction Update: July 17, 2019
Work scheduled for this week specifically includes:
- Rooftop piping for mechanical equipment at Westbrook
- Interior domestic water piping relocation at Henking
- Roof work at Pleasant Ridge and Glen Grove is scheduled for completion
- Metal coping work is ongoing at Lyon, Westbrook, Henking and Springman
- Attea’s new skylight is onsite and being assembled for installation
- Ceiling gridwork and tile re-installation at Springman, Henking and Glen Grove
- Masonry infills and patch work should be wrapping up this week at Pleasant Ridge, Glen Grove and Henking
- Insulation for ductwork and piping is underway
Weekly Construction Update, July 24, 2019
All deliveries are in and equipment is being set. Work scheduled for this week specifically includes:
- Tie-in to old chiller at Westbrook
- Insulating duct and pipe at all locations
- Floor protection removal and ceiling tile reinstallation
- Vertical unit ventilators are being installed at Springman
- Sheet metal flashing and trim work is near completion at all roof replacement locations
- New building generator installation at Attea
- New water heaters were installed at Springman
Weekly Construction Update: July 31, 2019
It's the last week of construction, and all hands are on deck! Work scheduled for this week includes:
- Duct and pipe insulation work at all locations
- Complete roofing sheet metal/coping at all locations
- Set the final piece of mechanical equipment at Attea
- Complete roof top piping and paint at Westbrook
- Complete installation & startup for the water heaters at Springman
- Perform start-ups on mechanical equipment
- Programming for all new mechanical units
Photos
Past Approvals
Village of Glenview Approval Process
On September 22, 2020 the Village of Glenview Plan Commission gave approval for construction projects at Henking, Lyon and Springman; the Westbrook construction project will be considered at the October 13, 2020 Plan Commission meeting. On September 23, the Appearance Commission gave preliminary approval for all projects.