Henking Referendum Progress
Coming Soon: Full-Day Kindergarten 2022-23
Ground Breaking
On May 17, 2021, the D34 Board of Education, Village Representatives, administrators and students broke ground at Lyon, Westbrook and Henking elementary schools and Springman Middle School.
An Overview
On March 17, 2020, the community approved a referendum for $119 million to allow District 34 to repair, replace and update our buildings.
This successful referendum signals that residents understand the importance of reinvesting in the school district’s capital assets. The impact of the referendum will positively impact the community for decades to come, and it will be felt at every school, in every classroom, by every District 34 student. We recognize that we are tasked with Building Future.
School Construction Schedule
Henking Timeline
- Week of 6/1/21 – 6/4/21
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week 12/13/21 - 12/18/21
- Week 12/20/21 - 12/25/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/21/22 -2/26/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 - 3/12/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 - 4/2/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week of 6/6/22 - 6/11/22
Week of 6/1/21 – 6/4/21
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Week of 7/19/21 - 7/24/21
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Week of 8/16/21 - 8/21/21
Week of 8/23/21 - 8/28/21
Week of 8/30/21 - 9/4/21
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Week of 9/20/21 - 9/25/21
Week of 9/27/21 - 10/2/21
Week of 10/4/21 - 10/9/21
Week of 10/11/21 - 10/16/21
RB
- Courtyard sheathing complete, continuing with remainder of building
MEP
- Ductwork, in wall rough and roof work
- Jensens, continuing with roof drains and in wall rough
- AMI, starting water lines
Elens & Maichin
- Continue with roofing
Mastership
- Starting MPR
- Beginning with courtyard masonry work
Nelson Fire Protection
- Completed overhead work (10/6) -- ***Minus stub in at existing building, TBD***
Week of 10/18/21 - 10/23/21
RB
- Continue exterior sheathing and air barrier work
- Skylight curbs and chases completed and dried in, coordinate with Elens & Maichin
MEP
- Ductwork, in wall rough and roof work
- Jensen's, continuing with in wall rough
- AMI, starting water lines
Elens & Maichin
- Roof install ongoing
- MPR metal work to begin
Mastership
- Masonry in courtyard ongoing
Madden Glass
- Begin setting window frames at MPR
Week of 10/25/21 - 10/30/21
RB
- Interior wall framing on going
Madden Glass
- Frames to begin arriving for windows
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's:
- In wall rough ongoing
- American:
- Have all exterior rough work complete
- Complete all overhead branch work
- In wall rough on going
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- Courtyard masonry ongoing - MOCK UP READY FOR REVIEW
- Begin MPR masonry
Week of 11/1/21 - 11/6/21
RB
- Interior wall framing ongoing
Madden Glass
- Begin install where openings are ready
- ***Large units with doors have been boarded up, material due in January***
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's
- In wall rough ongoing
- American:
- In wall rough on going
- Complete all overhead branch work
- Have all exterior rough work complete
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- Courtyard masonry ongoing
- Begin MPR masonry
Week of 11/8/21 - 11/13/21
RB
- Interior wall framing ongoing
Madden Glass
- Begin install where openings are ready
- ***Large units with doors have been boarded up, material due in January***
Monarch
- Board ups ongoing
- Set door frames
- Set barrowed light frames
MEP
- Jensen's
- In wall rough ongoing
- American:
- Have all exterior rough work complete
- Complete all overhead branch work
- In wall rough ongoing
- DeKalb
- Rough ductwork 95% complete
- AMI
- Overhead rough ongoing
- Pipe insulation starting where possible
- AMI
- Rough ductwork 95% complete
Elens & Maichin
- Roof install ongoing
- Fascia soffit blocking and parapet blocking ongoing
Mastership
- East and west elevations masonry
- MPR masonry ongoing
Week of 11/15/21 - 11/20/21
RB
- Complete interior wall framing EOW 11-12
MEP
- Jensens
- Complete in wall rough 11-12
- Call for inspections EOW 11-15
- American
- Complete all rough EOW 11-12
- Ready for inspections week of 11-15
- DeKalb
- Complete all rough duct work overhead equipment, etc and ready for drywall week of 11-22
- AMI
- Have all overhead and inwall work complete
- Ready for drywall week of 11-22
- Inspections
- AMI
- Complete all rough duct work overhead equipment, etc and ready for drywall week of 11-22
- Nelson
- Complete roof EOW
- Fascia and soffit work underway at MPR
- Mastership
- MPR complete
- East elevation complete
- S. elevation ongoing
Week of 11/22/21 - 11/27/21
RB
- Soffit framing ongoing
- Misc. framing of columns etc are ongoing
- First coat of mud complete at corridors
- Taping continues as availabl
- Drywall ongoing all areas
Monarch
- Door frames install ongoing (as available)
Madden Glass
- Continue install of available windows
MEP
- Jensens
- Continue with in-wall rough at large washrooms and storage area in MPR
- American
- Continue to follow behind RB at soffits to complete piping tie-ins
- DeKalb
- Continue with fan coil install, pipe and duct insulation ongoing overhead, instaff double wall duct in MPR
- AMI
- Continue with gas pipe to new addition RTU locations, continue with water pipe tie ins at fan coils
- Elens & Maichin
- MPR shingles ongoing
- Fascia and soffit metal work ongoing
- Mastership
- N. elevation of MPR corridor above existing building ongoing
Week of 11/29/21 - 12/4/21
RB
- Soffit framing ongoing
- Misc. framing of columns etc are ongoing
- First coat of mud complete at corridors
- Taping continues as availabl
- Drywall ongoing all areas
Monarch
- Door frames install ongoing (as available)
Madden Glass
- Continue install of available windows
MEP
- Jensens
- Continue with in-wall rough at large washrooms and storage area in MPR
- American
- Continue to follow behind RB at soffits to complete piping tie-ins
- DeKalb
- Continue with fan coil install, pipe and duct insulation ongoing overhead, instaff double wall duct in MPR
- AMI
- Continue with gas pipe to new addition RTU locations, continue with water pipe tie ins at fan coils
Elens & Maichin
- MPR shingles ongoing
- Fascia and soffit metal work ongoing
Mastership
- S. elevation complete and washed
- All equipment, debris and remaining materials removed from premises by EOW
Week of 12/6/21 - 12/11/21
RB
- Soffit framing and skylight framing on going
- Drywall on going all areas
- Taping ongoing in areas available
- In wall insulation on going
Monarch
- Complete Door frame install on going.
Madden Glass
- Continue install of available windows & glass ongoing
- MPR glass due in week of 12-20
Jensen’s
- Pipe insulation ongoing
- Final in-wall rough inspection Monday 12-6
American
- Wire feeding on going
DeKalb
- Insulation on going
AMI
- Insulation on going
Elens & Maichin
- MPR Fascia wood blocking on going
- Metal Cooping on going-currently being fabricated, begin installing this week.
Week 12/13/21 - 12/18/21
RB
- Soffit framing and skylight framing on going, to be completed this week
- Drywall on going all areas
- In wall insulation to be completed
Madden Glass
- Continue install of available windows & glass on going
Jensen’s
- Complete Pipe insulation
American
- Wire feeding on going
DeKalb
- Complete overhead Insulation
AMI
- Complete overhead Insulation on going
Elens & Maichin
- MPR Fascia wood blocking to be completed
- Metal Cooping to be completed
- Waiting on fascia and soffit metal
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
Week 12/20/21 - 12/25/21
RB
- Drywall on going in remaining areas
- Taping on going in available areas
- Painting-block fill to begin in MPR
Madden Glass
- Continue install of available windows & glass on going
- MPR upper window glass due in
American
- Wire feeding to be completed
DeKalb
- RTU install expected in January
Elens & Maichin
- Install Shingles
- Install metal wall panels
Week of 1/10/22 - 1/15/22
RB
May Decorating
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
Smart Interiors
- Final taping in MPR
- Taping in corridors.
Consolidated
Regency Tile
- Start installing bathroom wall tile in classrooms A1-A8
Madden Glass
- Continue install of available windows & glass on going
- MPR window glass completed week of 12-27 ***minus entryways***
American
Begin installing available light fixtures in Classrooms A1-A6
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
AMI
- Pipe Fan Coil at 9C week of 1-17
- Awaiting valves for fan coils, delivery 1-17-22
Elens & Maichin ***Temps have been too cold to continue work***
- Fascia and Soffit framing on going in preparation for finish work
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
- Fascia blocking is on going
Week of 1/17/22 - 1/22/22
RB
May Decorating:
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
Smart Interiors
- Final taping in MPR
- Taping in corridors.
Consolidated
Regency Tile
- Start installing bathroom wall tile in classrooms A1-A8
Madden Glass
- Continue install of available windows & glass on going
- MPR window glass completed week of 12-27 ***minus entryways***
American
Begin installing available light fixtures in Classrooms A1-A6
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
AMI
- Pipe Fan Coil at 9C week of 1-17
- Awaiting valves for fan coils, delivery 1-17-22
Week of 1/24/22 - 1/29/22
RB
May Decorating
- Painting on going
Alpine Acoustics
- Grid on going in Classrooms A1-A9
- Corridors on going
Smart Interiors
- Completing Taping in corridors.
- All other areas are completed
Madden Glass
- Classroom openings began 1-12
- Classroom openings are on going
- Corridor Entry units to begin
MEP
American
- Begin installing available light fixtures in Classrooms A1-A8
- Low Voltage pulling wire
DeKalb
- 1 fan coil remains to be installed at corridor 9C
- Continue installing diffusers and Duct work
AMI
- Pipe Fan Coil at 9C week of 1-17, moved to 1-24
- Awaiting valves for fan coils, delivery 1-17-22
Elens & Maichin
- Fascia and Soffit framing on going in preparation for finish work
- Waiting on Shingles to be installed, cannot install until fascia is complete.
- Waiting on metal wall panels
- Fascia blocking is on going
Week of 1/31/22 - 2/5/22
Consolidated
PSI
- Floor mitigation to begin in MPR and corridors. No access into building until 2-9-22 without prior coordination with Brian or Ian.
Regency Tile
- Tile on going in multi-use washrooms
- Complete grouting washrooms in classrooms Multi use washrooms
MEP
DeKalb
- 1 fan coil remains to be installed at corridor 9C
- Continue installing diffusers and Duct work
- Receive Radiant panels and install into grid.
AMI
- Pipe Fan Coil at 9C week of 1-17, moved to 1-24
- Awaiting valves for fan coils, delivery 1-17-22
- Tie in Radiant panels
Week of 2/7/22 - 2/12/22
Consolidated
- Begin installing VCT in MPR. ***Week of 2-14***
PSI
- Floor mitigation to begin in MPR and corridors. No access into building until 2-14-22 without prior coordination with Brian or Ian.
CSI
- Epoxy Floor finishes to begin in classroom washrooms A-1 thru A-8. No access into these washrooms until 2-14-22. Floors must be protected in order to do work in these spaces moving forward.
RB
- Frame out window benches in the classrooms, completing 2-7
- Carol Seating to complete final measurements for casework.
MEP
DeKalb
- Continue installing diffusers and Duct work
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
- Tie in Radiant panels. ***AMI completing remaining radiant panel tie ins in A-7, A-8 and Resource room, all other areas have been completed. ***
Week of 2/14/22 - 2/19/22
Week of 2/21/22 -2/26/22
Consolidated
- VCT on going in MPR.
- Classroom Carpeting install to begin following the ceiling tile installation.
MEP
DeKalb
- Cut in remaining diffusers
- Set remaining RTU, when available
AMI
- Complete any remaining valves for fan coils not yet completed
Jensen’s
- Plumbing fixture install on going.
Alpine Acoustics
- Complete any remaining grid work
- Begin installing ceiling tiles.
Week of 2/28/22 - 3/5/22
Consolidated
- Complete Carpet installs in classrooms
- Tile to be completed
CSI
- Waiting on materials to arrive to get work started.
RB
- Ceiling Grid and ceiling pads install
E&M
- Fascia and soffit install on going
- Wall panels to begin
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Week of 3/7/22 - 3/12/22
Consolidated
- Complete VCT in corridors
- Epoxy Floors on going (Pending material availability)
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Jensens
- Receive plumbing fixtures
- Begin installing plumbing fixtures
Week of 3/14/22 - 3/19/22
Consolidated
- Complete VCT in corridors
- Epoxy Floors on going (Pending material availability)
MEP
DeKalb
- Continue installing diffusers and Duct work at vestibules
AMI
- Awaiting valves for fan coils, delivery 1-17-22***Three locations are still waiting on the valves, all other areas have been completed. ***
Jensens
- Receive plumbing fixtures
- Begin installing plumbing fixtures
Week of 3/21/22 - 3/26/22
N/A
- Relocate construction office to resource room
E&M
- Finishing tie-ins and roof flashing/patching
Consolidated
- Finished up flooring in corridors and rooms 95%
Carol seating
- Will be out mid-week to deliver and start installing case work
Alpine
- Ceiling grid 95% complete
Jensen
- Continued work on installing plumbing fixtures
Hygineneering
- Abetment is on going
Week of 3/28/22 - 4/2/22
Week of 4/4/22 - 4/9/22
Madden Glass
- Finish installing SF Threshold
- Finish setting last of SF units in MPR
Consolidated
- Finish patch-in work in the classrooms and finish base (95%)
Jensen
- Continue installing plumbing fixtures
Reimer
- Start surveying for site work to commence
Oleson
- Start draining lake Henking and investigate remaining structure
Week of 4/11/22 - 4/16/22
Week of 5/2/22 - 5/7/22
Madden glass
- Finish store fronts
Consolidated
- Finish flooring in MPR, finish base (95%)
Jensen
- Finish tying in down spots
Reimer
- Site grading on West side and South side to continue
Oleson
- Waiting for decision on Lake Henking with new manhole and pipe work.
American Electric
- Start to trim classrooms. Change switch plates to stainless steel.
Eagle
- Frame sidewalks, stairs. Stone and pour concrete. East, West, and South.
Eilens & Maichin
- Finish facia and gutters
Week of 5/9/22 - 5/14/22
Week of 5/16/22 - 5/21/22
Madden Glass
- Finish two windows in MPR
Reimer
- Site grading on West side and South side to continue. Start filling in black dirt.
Eagle
- Frame sidewalks and pour south side
Elens & Maichin
- Finish facia and gutters and screens.
K & L
- Pave West side playground. Stone and prep east side on top of storm trap.
Action Fence
- Layout and install fence.
Seibert
- Start planting trees shrubs and laying sod west side.
Week of 5/23/22 - 5/28/22
Week of 5/31/22 - 6/4/22
Madden glass
- Finish two windows in MPR
Reimer
- Site grading on West side and South side to continue. Start filling in black dirt.
Eagle
- Frame sidewalks and pour south side.
Eilens & Maichin
- Finish facia and gutters and screens.
Action Fence
- Layout and install fence.
Seibert
- Start planting trees shrubs and laying sod west side.
American Electric
- Start to disconnect power in rooms and install temp lighting for demo.
Jensen Plumbing
- Disconnect bathroom fixtures for demolition. Start classroom disconnects.
DeKalb
- Drain HVAC system 6/2
AMI
- Drain HVAC system 6/2
Johler
- Start demo of rooms 11 & 13
Movers
- Move furniture in classrooms.
Week of 6/6/22 - 6/11/22
Phase 1 Project Scope
-
1 Story Building Addition & Sitework
-
8 Kindergarten Classrooms with Single User Toilets
-
2 Multi-User Toilets (Boys & Girls)
-
1 Single User Toilets
-
1 Multipurpose Room
-
2 Asphalt Play Areas with Basketball Hoops
-
Grass Courtyard with Trees
-
1 Storm Water Detention System
-
Landscaping
What can we expect?
The construction at Henking will add space for full-day kindergarten, include a multi-purpose room addition and update classrooms (acoustic, flooring, other).
In addition to the extra space, construction will improve the following areas of Henking School:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- New kindergarten addition, including multipurpose room
- Classroom environment
Phase 1 Timeline
February 2021
March 2021
May 2021
- Ground Breaking (May 17, 2021
- Construction Commencement (pending permit approvals)
August 2022
Frequently Asked Questions
- When will construction start and end?
- Will construction workers be inside the school building?
- What if construction noise impacts the classroom?
- Will construction dust impact the air quality in the classroom?
- Will our current parking be affected by the construction?
- What do I do if I see a safety issue?
When will construction start and end?
Will construction workers be inside the school building?
What if construction noise impacts the classroom?
Will construction dust impact the air quality in the classroom?
Will our current parking be affected by the construction?
What do I do if I see a safety issue?
Contact your school principal or Director of Operations Steve Ruelli.