Springman Referendum Progress
Construction Progress
Ground Breaking
On May 17, 2021, the D34 Board of Education, Village Representatives, administrators and students broke ground at Lyon, Westbrook and Henking elementary schools and Springman Middle School.
An Overview
On March 17, 2020, the community approved a referendum for $119 million to allow District 34 to repair, replace and update our buildings.
This successful referendum signals that residents understand the importance of reinvesting in the school district’s capital assets. The impact of the referendum will positively impact the community for decades to come, and it will be felt at every school, in every classroom, by every District 34 student. We recognize that we are tasked with Building Future.
School Construction Schedule
Springman Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week of 12/13/21 - 12/18/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/28/22 - 3/4/22
- Week of 3/7/22 - 3/11/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 - 4/2/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 - 4/23/22
- Week of 4/25/22 - 4/30/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week 6/6/22 - 6/11/22
- Week of 6/13/22 - 6/18/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Albrecht
- Finish backfill + stone at area G
- Dig fluid cooler pad
- finish haul road to trailer
Eagle
- Pour storm trap
- Pour fluid cooler pad
AJ Oleson
- Finish sanitary piping and structures
- Locate and pick up existing piping in courtyard area to complete fluid cooler pad
- Pour fluid cooler pad
Johler
- Finish concrete demo at South Gymnasium
Jensen
- Start underground in science addition
- Complete any re-piping at area D/F to mechanical room
Carey Electric
- Finish reconnect mechanical room panel
- 220v for mason
- Disconnect CUV at rooms
FE Moran
- Reconnect piping at mechanical room
- CUV relocation
DCG
- Finish any temp roofing at gymnasium to keep existing watertight
Week of 7/19/21 - 7/24/21
Albrecht
- Start pad/excavate at gymnasium
- Slab stone at Area G with UG plumbing is complete
AJ Oleson
- Locate and pick up existing piping in courtyard area to complete fluid cooler pad
Johler
- Demo at overhang area G/E
Jensen
- Finish underground in science addition
- Complete any re-piping at area D/F to mechanical room
Carey Electric
- 220v for mason
- Work with mason at interior wall starter course (if needed)
FE Moran
- Reconnect piping at mechanical room
- CUV relocation
- Fluid cooler pad
Mastership
- Start interior wall starter course below slab (when plumbing is complete)
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Albrecht
- Backfill at gymnasium
- Crane pad for spancrete
Eagle
- F/R/P footings at gymnasium
AJ Oleson
- Reconnect any existing lines needed
Carey Electric
- CMU rough
FE Moran
- Duct layout and thermostat rough with mason as needed
Mastership
- Exterior/interior walls
Hargrave
- Window protection
Jensens
- Complete pit and ug rough for existing lines in area F
- In wall rough in area G
Week of 8/16/21 - 8/21/21
Albrecht
- Backfill at gymnasium
- Stone at pad
Eagle
- Finish all frame/reinforce/pour (F/R/P) footings at gymnasium
AJ Oleson
- Reconnect any existing storm lines
Carey Electric
- CMU rough at Area G
FE Moran
- Thermostat / control rough with mason, as needed
Mastership
- Finish first floor walls and stairwells at Area G
Jensen's
- In wall rough in area G
Spancrete
- Dead men install
- Start precast install at Area F
Week of 8/23/21 - 8/28/21
Week of 8/30/21 - 9/4/21
Albrecht
- Stone at Area F pad
Eagle
- Frame pour area of wall after gas line relocation
AJ Oleson
- Reconnect any existing storm lines
Carey Electric
- CMU wall rough at Area G/F
FE Moran
- Thermostat/control rough with mason as needed
Mastership
- First floor load bearing walls at Area F
Jensens
- In wall rough at Area G
Spancrete
- Grout panels
M&I
- Start second floor steel and deck at Area G
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Albrecht
- Stone at Area F pad
Eagle
- Pour at 2nd floor deck at Area G 9/14
Carey Electric
- CMU rough at Area G/F
FE Moran
- Thermostat / Control rough with mason as needed
Mastership
- Finish load bearing walls at Area F
- Second floor walls at Area G
- Fluid applied air barrier at Area G
- Mock-up
Jensens
- In wall rough at Area G
Spancrete
- Finish caulking panels
M&I
- Lower roof framing at Area F
Hargrave
- Safety rails and temp stairs at Area G, second floor, 9/13
Week of 9/20/21 - 9/25/21
Week of 9/27/21 - 10/2/21
Carey Electric
- CMU wall rough at Area G/F
FE Moran
- Thermoset / Control rough with mason, as needed
Mastership
- Finish face brick at North wall Area F
- Bearing walls at Area F
- Face brick at Area G
Jensens
- Chase wall rough at Area G
- UG at Area F
- Roof drains at Area F
Spancrete
- Finish caulking brick panels
- Remove structural supports 10/28 AM
M&I
- Finish lower roof framing and deck at Area F
- Finish gym roof framing and deck
- Start Area G roof framing
Albrecht
- Backfill at Northwest corner of Area F
- Stockpile stone in Area F after M&I equipment is out
- Stone areas of pad after UF plumbing is complete and prepare for electrical UG
Week of 10/4/21 - 10/9/21
Mastership
- Finish face brick at Area G
- All bearing walls at Area F need to be complete and read for steel install by 10/5
Johler/Hargrave
- Demo at front company
Carey Electric
- CMU walls rough at Area G/F
- UG at Area F
FE Moran
- Thermostat/Control rough with mason, as needed
- Ductwork install at Area G first floor
Jensen's
- UG at Area F
M&I
- Finish steel frame at Area F lobby before epic deck arrives on 10/11
- Finish roof framing and decking at Area G
Doherty
- CFMF at Area F soffits
Spancrete
- Install leave out panels
Albrecht
- Stone remainder of pad in Area F
Week of 10/11/21 - 10/16/21
Carey Electric
- CMU rough at Area G/F
- UG at Area F
FE Moran/Amber
- Duct work at first floor Area G
- Roof cubs install
- Gas line take offs
Mastership
- Face brick at Area G/F
- Demo and patch at existing - T&M RFP-014SP
Jensen's
- UG at Area F
- Roof drains at Area F/G
Spancrete
- Finish caulking brick panels (caulk color has been approved)
- Remove wall bracing after roof
M&I
- Finish gym roof deck
- Epic deck at lobby
Albrecht
- Stone remainder at Area F pad
- Haul out spoils and dress up Haul Road
Doherty
- CFMF soggits at Area G/F
DCG
- Start roof blocking at available areas (coordinate with Doherty)
Eagle
- Prep/pour SOG at east and south elevations of F (Thursday-Friday)
Week of 10/18/21 - 10/23/21
Carey Electric
- CMU rough at Area G/F
- UG at Area F lobby and gym
FE Moran/Amber
- Finish ductwork at first floor Area G
- Roof curb install
- Gas lines
Mastership
- Face brick at Area G/F
- Demo and patch at existing
- Brick wash
Jensen's
- DWV
- Roof drains at Area F/G
M&I
- Stairs in south tower Area G
Albrecht
- Stone remainder of pad in Area F
Doherty
- Finish CFMF soffits at Area G/F
DCG
- Start roof blocking at available areas (coordinate with Doherty)
Eagle
- Prep/pour SOG at all available sections
Hargrave
- Board up at all locations
Nelson
- FP pipe install at Area G, first floor
Week of 10/25/21 - 10/30/21
Carey Electric
- Any in wall rough with mason
FE Moran/Amber
- Set RTU
- Temp heat rough in
Mastership
- Finish front entry
- Finish face brick at elevations that have roof blocking and vapor barrier completed
- Demo and patch at existing
- Brick wash at all available locations
Jensen's
- DWV
- Roof drains at Area F/G
- Storm line at Fluid coolers (to be coordinated by N&A)
M&I
- Stairs in north tower Area G
- Front canopy
Doherty
- Finish CFMF soffits at Area F
- Start CFMF at storefront locations Area F
DCG
- All roof blocking to be complete
- Install stainless steel flashing at roof blocking
- Material delivery
- Start Area G roof
Eagle
- Prep/pour SOG at remaining locations
- Prep/pour south stairwell at Area G
- Doweling at Area F interior walls
Hargrave
- Finish board up at all locations
Week of 11/1/21 - 11/6/21
Carey Electric
- Any in wall rough with mason Area F interior walls
FE Moran/Amber
- Temp heat rough in
- Coordinate any masonry openings in Area F
Mastership
- Finish face brick at elevations that have roof blocking and vapor barrier completed
- Demo and patch at existing
- Brick wash at all available
- Interior walls at Area F
Jensen's
- DWV
- Roof drains at Area F
- Storm line at fluid coolers (to be coordinated by N&A)
M&I
- Canopy at front entry
Doherty
- Finish CFMF soffits at Area F
- Start CFMF at storefront locations Area F
- Vapor barrier at Area G soffits
DCG
- All roof clocking to be complete
- Finish area G roof
- Start gym roof
Eagle
- Pour missing foundation at existing
- Prep/pour North and South stairwell at Area G
- Doweling at Area F interior walls
Hargrave
- Finish Board up at all locations
Madden
- Start CW install at Area G
Week of 11/8/21 - 11/13/21
Week of 11/15/21 - 11/20/21
Week of 11/22/21 - 11/27/21
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in at gymnasium
FE Moran/Amber
- Set RTU in Area G
- Cut wall openings at second floor Area G
- Second floor duct work
- Finish all chase wall rough at Area G
Mastership
- Finish all brick wash
- Interior walls @ Area F
Jensen’s
- DWV
- In wall rough as needed @ Area F
- Finish Area G Chase wall rough and have inspected
Doherty
- Start Roof top unit detail as described in M3.00 SP***
- Start firring for Tectum in Area G***
- Frame Interior soffits and bulkheads @ Area G
- Finish all storefront CFMF in Area F
DCG
- Finish West and North lower roofs @ Area F
- Start Tie in @ Existing
- Field Measure for insulated Panels in available locations***
- Coping @ all available ***
Hargrave
- Finish Area G/F door frames***
Madden
- CW install @ Area G
- S/F install @ Area F
- Glass install @ all available
Week of 11/29/21 - 12/4/21
Mastership
- Finish interior walls @ Area F
- Chase walls @ Area G
Carey
- CMU Rough with Mason
- Rough in @ Gymnasium
Jensen’s
- DWV
- CMU Rough with Mason
Doherty
- Frame interior soffits and bulkheads
- Roof top unit detail @ area F
- Tectum panel install
- Spray insulation @ Area F
DCG
- Tie- in @ all existing/new
- Insulated Metal panel/ coping install
Week of 12/6/21 - 12/11/21
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in @ Gymnasium
FE Moran/Amber
- Set RTU in Area G (Please confirm exact date) *** ***
- Cut wall openings @ 2nd Floor Area G *** ***
- 2nd floor duct work ***
- Finish all Chase wall rough @ area G ***
- Start Gymnasium Ductwork
Mastership
- Finish all brick wash *** ***
- Interior walls @ Area F North locker rooms ***
- Start/ Finish Chase walls @ Area G
Jensen’s
- DWV
- Coring @ Gymnasium
- Finish storm drain Tie in
- Chase wall rough @ south locker room Area F
Doherty
- Roof top unit detail as described in M3.00 SP
- Tectum install @ Area G 2nd floor ***
- Frame Interior soffits and bulkheads @ Area G *** ***
- Finish bulkhead at Interior storefront front entry
- Finish all waterproofing and insulation ***
DCG
- Field Measure for insulated Panels in available locations*** ***
- Coping/ insulated panels @ all available *** ***
Hargrave
- Finish Area G/F door frames***
Madden
- S/F install @ Area F
- Glass install @ all available
Nelson
- FP piping @ 1st floor science rooms
- FP piping @ Gymnasium
Week of 12/13/21 - 12/18/21
Mastership
- Finish interior walls @ Area F ***
- Finish Chase walls @ Area G
- Chase walls @ South Locker rooms
Carey
- CMU Rough with Mason
- Rough in @ Area F
Jensen’s
- Chase wall Rough @ North locker rooms
- CMU Rough with Mason
Doherty
- Frame interior soffits and bulkheads
DCG
- Insulated Metal panel/ coping install
Nelson
- FP piping @ 2nd floor science rooms
Week of 1/10/22 - 1/15/22
All Trades
- Last chance to get all material and garbage out of area G before paint starts
- All work prior to paint should have been done last week
Carey Electric
- Any in wall rough with mason Area F interior walls
- Rough in @ Gymnasium
- LV rough in Area F
- Rough @ North Lobby Soffits
FE Moran/Amber
- Duct work in Area F
- Duct @ North lobby soffits
Mastership
- Finish all walls in Area F except for chase walls at gym curtain
- Caulk exterior
- Finish all bullnose before paint
- Start rub down walls in area F
Jensen’s
- Supply rough @ Area F
- Pipe insulation @ Area F
Doherty
- Framing and drywall in stairwells
- Frame west lobby soffits
- Finish taping and sanding @ all Area G soffits
- Start Block fill @ 2nd floor Area G?
DCG
- Field Measure for insulated Panels in available locations*** *** *** *** *** ***
- Coping/ insulated panels @ all available *** *** *** *** *** ***
- Temp tie in at existing by front entry *** ***
- Pipe portal in gymnasium north end and for signage on west end *** ***
Hargrave
- Coordinate door frame installs with Mason for Area F
- Finish any previously installed frames complete (Bondo/caulk) *** ***
- Remove temp wall material and garbage
- Gymnasium curtain track install
- Framing @ casework chase locations
Madden
- Cover installs
- West vestibule S/F install
Nelson
- FP piping @ North lobby soffits
- FP piping at All remaining Area F
- All fire caulking complete in area G
Week of 1/17/22 - 1/22/22
Week of 1/24/22 - 1/29/22
All Trades
Carey Electric
- Rough in @ Area F
- LV rough in Area F
FE Moran/Amber
- Duct work in Area F
Mastership
- Prep walls for paint in Area F
- Chase walls @ Gym curtain soffit
- Interior Caulk @ Area F
Jensen’s
- Supply rough @ Area F
- Pipe insulation @ Area F
- Move storm piping @ gym soffit
Doherty
- Finish taping and sanding drywall @ stairwells
- Start framing Gym curtain soffit
- Framing @ Soffit RFP 014
- Finish painting Area G
DCG
- Field Measure for insulated Panels in available locations
- Coping/ insulated panels at all available
- Pipe portal in gymnasium north end and for signage on west end
Hargrave
- Finish installing any frames
- Caulk and Bondo Frames in Area F
- Remove all temp board up garbage from gym
Madden
- Finish all frame covers and sunshades
- Finish all exterior caulking
- East side of North lobby vestibule S/F install ***
Nelson
- All fire caulking complete in Area F
- Area F rough complete
Week of 1/31/22 - 2/5/22
Mastership
- Finish Gym curtain chase walls
- Finish interior Caulk at Area F
- Finish wall prep@ Area F
Carey
- Rough in at Area F
- LV rough at Area F
Jensen’s
- Supply rough in Area F
- Pipe insulation at Area F
Doherty
- Start Paint at Area F
- Tape Sand Drywall at Area F
DCG
- Insulated Metal panel / coping install
Moran/Amber
- Finish Area F ductwork / piping
Madden
- West lobby S/F install
Week of 2/7/22 - 2/12/22
All Trades
- Work on getting any materials out of Area G. Must be out for floor mitigation starting 2/17
Carey Electric
- Rough in @ Area F
- LV rough in Area F
- Electrical trim @ Area G
- Lighting @ Area G
FE Moran/Amber
- Finish All ductwork @ Area F
- Trim out @ Area G
Mastership
- All walls need to be prepped and ready for paint @ Area F
- Demobilize and clean up in Gymnasium
- Finish ALL Interior Caulk @ Area F
- Wash Brick @ North lobby
- Fire Caulk @ all Rated walls
Jensen’s
- All Pipe insulation to be complete
- Valve tags, stickers, fire caulk
Doherty
- Finish ceiling grid at Area G
- Finish Gym curtain soffit + taping and sanding complete
- Framing @ Soffit RFP 014
- Finish painting frames at Area G
- Block fill/Prime/ Paint at Area F Storage Area, West Lobby, North and South Locker rooms
DCG
- Coping/ insulated panels at all available
- Pipe portal in gymnasium north end and for signage on west end
Hargrave
- Finish prepping frames for paint
Madden
- Finish all frame covers and sunshades
- Finish all exterior caulking
- S/F install at West lobby
Nelson
- Measure heads at all drop ceiling locations at Area G (coordinate with N&A first to make sure grid is complete)
Week of 2/14/22 - 2/19/22
Week of 2/28/22 - 3/4/22
All Trades
- All Materials and Equipment needs to be removed from the Gymnasium by the end of this week
Carey Electric
- Pull Fire Alarm at Area F
- Install projector and screens after Gym ceiling is painted
- Pipe /wire electric heaters
- Light install at all available in Area F
- Re-pipe at Main entrance Doors for new Electric Strike Location
FE Moran/Amber
- Finish All ductwork at Area F
- Pull communication wire at Area F
- Install fabric duct in gym after ceiling is painted
- Install electric Heaters
- Install ceiling diffusers where available
Mastership
Jensens
Doherty
- Finish Wall Paint in Gymnasium ceiling + walls
- Finish taping soffit in North Lobby
- Ceiling grid in North locker rooms, PE offices, G 100 lobby/ vestibule, West Lobby and North Lobby
- Drywall at G118 Vestibule
DCG
- Start metal coping and flashing
Hargrave
- Madden
- Finish all caulking
- S/F install at West lobby
- Install Mull Extensions at Area G
- Finish Door Installs
Nelson
- Start Sprinkler head install at Area F Grid locations
- Move line at G 118 Vestibule
Consolidated/PSI
- Start VCT install at 2nd floor Area G
Week of 3/7/22 - 3/11/22
All Trades
- All Ceiling trim and above grid work needs to be completed in locker rooms by the end of this week
Mastership
Carey
- Electrical Trim at any Area F painted locations and ceiling grid locations
Doherty
- Ceiling grid complete by 3/8
DCG
- Coping /Flashing install
Moran/Amber
- Trim at any ceiling grid locations
Madden
Nelson
Consolidated
- Finish 2nd floor VCT Install
- Start 1st floor VCT Install
- Start Gymnasium Floor Mitigation
Week of 3/14/22 - 3/19/22
All Trades
- All Ceiling trim and above grid work needs to be completed in locker rooms by the end of this week
Hargrave
- Start Gym Partition Install
Carey
- Electrical Trim at any Area F painted locations and ceiling grid locations
- Speaker install at Gymnasium
Doherty
- Front Entry Ceiling
DCG
- Coping /Flashing install
Moran/Amber
- Trim at any ceiling grid locations
- Fabric Duct Install
Madden
Nelson
Consolidated
- Finish 1st floor VCT Install
- Start floor mitigation in North lobby
- Start Epoxy flooring in locker rooms
Week of 3/21/22 - 3/26/22
All Trades
- All Fire Caulking/Safing @ wall penetrations needs to be complete for Above Ceiling Inspection on 3/28
Carey Electric
- Transformer pad install
- Re-pipe @ Main entrance Doors for new Electric Strike Location
- Speaker installs @ Gymnasium
- IDF Rack install @ Area G
- All above ceiling ready for Inspection on 3/28
FE Moran/Amber
- Finish All communication wire @ Area F
- Finish All Through Wall Flashings
- Finish All Ceiling Diffusers in Area G/F
- All Above ceiling work completed
Eagle
Doherty
- Finish All Ceiling Grid
DCG
- Metal coping and flashing
Hargrave
- Gym equipment install
Madden
- Finish all Interior / Exterior caulking/ Door Hardware
Nelson
- Finish Sprinkler head install @ Area F Grid locations
Consolidated/PSI
- Moisture Mitigation @ North/West lobbies
Week of 3/28/22 - 4/2/22
All Trades
Hargrave
- Finish gym Equipment install
- Door install at Area G
Carey
- MDF Rack Install at Area G
- Gym equipment hook ups
Doherty
- RFP 014 soffit framing
- Drop Front entry ceiling
- Start ceiling tile install (Locker rooms/ Area g)
- Plan on exterior painting at Precast as soon as weather allows
DCG
- Coping/Flashing install
Moran/Amber
- Finish All Above ceiling work. All Flashings Sealed
Madden
Nelson
Consolidated
Week of 4/4/22 - 4/9/22
Carey Electric
- Re-pipe at Main entrance Doors for new Electric Strike Location
- AV rack install at Atea G
- Fire Alarm Inspection
- Gym equipment control install
- Pipe/ Wire to DOAS/RTU
FE Moran/Amber
- Finish trimming out at area G
- Finish Diffusers at Area F
Doherty
- Drywall/Tape at North/West Lobby vestibules
DCG
- Finish Metal coping and Flashing
Hargrave
- Finish Gym equipment install
- Start casework install at Area G
- Finish casework atArea F
- Finish Solid Surface Bench
- Start Scoreboard Install
Madden
- Finish Caulking/Door Hardware
Nelson
- Inspection set for Thursday
Consolidated/PSI
- Stock/ Start VCT in North/West lobbies/PE Offices
- Start Epoxy in Locker rooms
Jensens
- Water Meter Install
Week of 4/11/22 - 4/16/22
Hargrave
- FEC Install
- Door install at Area G
- Folding Partition Install at Science Rooms
- Finish Scoreboard Install
Carey
- Gym Equipment control install
Doherty
- RFP 014 soffit framing
- Fix any Degraded Areas on Air Barrier
- Drop Front entry ceiling
- Start ceiling tile install
- Plan on exterior painting at Precast as soon as weather allows
FE Moran
- RTU Install and All Associated Duct Work and Control Wiring
Jensens
- Begin Plumbing Trim
Nelson
Consolidated
- Finish Epoxy flooring in locker rooms
- Finish VCT @ North/West Lobbies
Week of 4/18/22 - 4/23/22
All Trades
Carey Electric
- AV rack install at Area G
- IDF Rack Install at area F
FE Moran/Amber
- RTU-2 Install and any Associated Ductwork/Control Wiring
- Finish all diffusers/grills
- Install Disconnects at RCP’s
Doherty
- Repair Air Barrier
- Install Plywood in IDF Rooms
- Wall Covering in North Lobby
- Access Panel Install
DCG
- Start Metal panel Install
Hargrave
- Finish casework install at Area G
- Finish Solid Surface Bench
- Finish Scoreboard Install
- Install Door Frames A 100-B, G 100-E
- Start Folding Partition at Science Rooms
- Bath Partition Install
- Projector Screen Install
Madden
- Finish Caulking/Door Hardware
Consolidated/PSI
- Finish VCT in PE offices, North lobby and IDF Room
- Start North Stairwell at Area G
- Floor protection at Locker Rooms
Jensens
- Start Plumbing Trim at Locker rooms
Nelson
- Install All Trims
Week of 4/25/22 - 4/30/22
All Trades
- All Ceiling and wall work to be completed in Gymnasium and Storage Room
- All Material and Equipment to be removed from the Gymnasium and Storage Room
Hargrave
- FEC Install
- Door/Hardware install at Area G
- Finish Folding Partition Install at Science Rooms
- Install Bath Accessories
Doherty
- Finish Ceiling Tile Install
- Plan on exterior painting at precast as soon as weather allows
FE Moran
- Finish RTU Install and All Associated Duct Work/Control Wiring
- Connect Fume Hood/Duct Work
Jensens
- Finish Plumbing Trim at Locker rooms
- Start Trim at Science Rooms
DCG
- Metal Panel Install
Consolidated
- Finish North Stairwell @ Area G
Mastership
- Apply Anti-Graffiti Spray
Week of 5/2/22 - 5/7/22
Carey Electric
- AV rack install at Area G
- Outlet install at are G casework (coordinate with Hargrave)
FE Moran/Amber
- RTU-2 Install and any Associated Duct work/Control Wiring
- Finish all diffusers/grills
- Install Disconnects at RCP’s
- Fume hood Vent Connection 5/5
Doherty
- Wall Covering in North Lobby
- Access Panel Install
- Paint touch- up in Gym and Area F storage
- Paint HM Doors
DCG
- Finish RFP 014 Existing Roof/ Area G Roof
Hargrave
- Finish casework install at Area G
- Install Door Frames A 100-B, G 100-E
- Finish Bathroom Accessories
- Swing HM Doors/Wood Doors
- Finish Fume Hood Install by 5/4
Jensens
- Trim in Area G
Mastership
- Apply Anti-Graffiti Spray
- Replace Damaged Face Brick @ 2 locations
Week of 5/9/22 - 5/14/22
Week of 5/16/22 - 5/21/22
Carey Electric
- All LV complete
- Outlet install at are G casework (coordinate with Hargrave)
- Light Pole Feeds at west End
FE Moran/Amber
- Finish all diffusers/grills
Doherty
- Wall Covering in North Lobby
- Finish Paint at exterior precast
DCG
- Finish RFP 014 Existing Roof/Area G Roof
- Metal soffit panels
Hargrave
- Finish Bathroom Accessories
- Finish HM/Wood door/Hardware Install
- Scoreboard Install
- Start Cleaning (5/19-5/20)
Mastership
- Apply Anti-Graffiti Spray
- Replace Damaged Face Brick at 2 locations
- Enlarge access Panel Openings
- Infill at extra FEC
- Move Equipment to Front of Site
Consolidated
- Seal Concrete at Storage Area
- Finish Vinyl base/ Carpet squares (coordinate with PSI)
- Carpet at vestibules
Week of 5/23/22 - 5/28/22
Week of 5/31/22 - 6/4/22
Hygieneering
- Begin Abatement
Phase 2 MEP’s
- Cut /Cap at Demo Areas 6/2
- Safe all Areas for Demo 6/2
- Begin 2nd Floor Demo 6/4
- Begin locker room/Bathroom demo 6/2
LoDestro
- Begin 2nd Floor Demo 6/4
- Begin locker room demo 6/2
- Floor protection install 5/31
Johler
- Begin/Finish Demo at Area C 6/1‐6/3
- Begin ceiling demo at Area E/D 6/4
- Begin Stairwell Demo 6/4
Phase 1 MEP’s
- Begin demo at Area C 6/1
Flo‐tech
- Classroom Unit ventilator demo
Hargrave
- Floor/Casework protection at Area C (coordinate with Johler)
Doherty
- Finish Paint touch‐ups
- Finish Exterior Paint
DCG
- Metal Soffit Panels at Area G
Carey
- Run Feeds for RTU‐1
FE Moran
- Start Up RTU‐1 6/3
Week 6/6/22 - 6/11/22
Hygieneering
- Continue Abatement
MEP’s
- Finish 2nd Floor Demo
- Begin 1st Floor Demo/Mechanical room
LoDestro
- Finish 2nd Floor Demo
- Begin 1st Floor Demo/Mechanical Room
- Begin concrete slab demo
M&I
- Steel Joist Reinforcement
Mastership
- Window Infill/Walls at Area C
Albrecht
- Excavation at Stairwell
Flo‐Tech
- Fluid Cooler/Pad Removal
DCG
- Metal Soffit Panels at Atea G
Week of 6/13/22 - 6/18/22
Phase 1 Project Scope
-
2 Story Building Addition & Sitework
-
1 Gymnasium with Bleachers & Operable Partition
-
4 Locker Rooms (Boys & Girls)
-
4 P.E. Offices
-
Lobby & Vestibules
-
4 Science Labs with 2 Prep Labs
-
2 Multi-User Toilets (Boys & Girls)
-
2 Single User Toilets
-
2 Stair Towers
-
1 Storm Water Detention System
-
Landscaping
What can we expect?
The following areas will be focused on to improve Springman:
- Upgrading science labs to meet national standards*
- Creating additional special education spaces
- Consolidating and relocating offices to increase security and provide students with better access to staff
- Reconfiguring stairways to improve safety and meet current codes
- Relocating the cafeteria to improve the student experience, supervision, acoustics, and ADA accessibility
- Moving locker rooms out of the basement to improve supervision and accessibility
*Attea labs will also be updated so all D34 middle school students learn in labs that support Next Generation Science Standards.
Construction will also focus on the following:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Site reconfiguration including underground stormwater detention
- New entry addition at main office
- Renovation of east gym to become new cafeteria
- Mechanical, electrical and plumbing replacement
- New south gym addition
- Classroom environment (acoustics, flooring, other)
Phase 1 Timeline
February 2021
March 2021
May 2021
- Ground Breaking (May 17, 2021
- Construction Commencement (pending permit approvals)
August 2022
Frequently Asked Questions
- When will construction start and end?
- Will construction workers be inside the school building?
- What if construction noise impacts the classroom?
- Will construction dust impact the air quality in the classroom?
- Will our current parking be affected by the construction?
- What do I do if I see a safety issue?
When will construction start and end?
Will construction workers be inside the school building?
What if construction noise impacts the classroom?
Will construction dust impact the air quality in the classroom?
Will our current parking be affected by the construction?
What do I do if I see a safety issue?
Contact your school principal or Director of Operations Steve Ruelli.